RE:RE:RE:RE:RE:RE:Lets talk NP for a momentStep 1. Fn gets on board.
step 2. get permit.
That might happen in 2 years if copper price jumps.
Then a year of stripping while they do mill ground work.
Then 2 years to build and ramp mill.
So 4 years in a perfect world.
Mine manpower is the big prob. Teck has to dilute there skilled force to send to there 2 mega chile mines.
That leaves tko the best fit. They could dilute skills at gib to supply np.
nf