RE:RE:RE:RE:RE:New Press Release - Avanti Helium Announces Resignation of DirectorLatest target for production is end of Q3/early Q4, six months later than original estimated production date. From the last MD&A issued at the end of April, there was no mention that IACX had shipped any of the modules for the HRU to site. Based on the recently revised target date, IACX won't ship any equipment to site until late July or early August. This is based on previous PRs that stated IACX would ship equipment in December of '23 for production in early Q1 of 2024. Not sure why the delay, but maybe IACX held back on the fabricaton of the HRU modules until they were more confident that Avanti would actually sell what was being produced (i.e. absence of a signed offtake agreement, but have now signed an agreement with Edelgas to help market and sell Avanti's production). There's no point building the HRU if you can't get paid for the production.