- When will you head into production?
We are still a few years from production. We still need the feasibility, which alone will take about 18 months.
- Can you speak on hole 30?
As all other companies in the mining industry, we are experiencing delays in assay results due to lab delays.
- Drill rigs? Resource Estimates for Infanta?
Currently there are 4 drills on site, and number 5 will be ready after the holidays, early Jan 2022. Romenera el Cura will get another 3 but the end of Q1 on 3 deposits. Fanta will drilled off for resources Q1
- IBW?
Geophysical just came in and the results will great so far. We are doing analysis on the report to put out a press release.
- Nuevo Tintillo?
There are people on the ground now. The formal start is Q1 on the 25km property between Tio Tinto and Aznal collar.
- How will reverse faulting at La Infanta affect economics?
This actually brought deeper portions of the deposit up higher which is presenting an opportunity for 2 deposits.
- Aznal Collar court update?
No new information at this time
- What is the status on the treasury?
Currently at about 25M with warrants well in the money. Sprott exercised his warrants which provided more capital. We would add that costs are significantly cheaper over here - we are looking at about half the costs of companies in Chile.
- Catalysts in the next while?
Resolution of the Aznal and permitting for the romenera (3 drills)