Milling Timeline & Self Financing Here is what I see as a timeline to milling & the start of self financing this project
1] Pre feasibility study 2 months {complete mid November}
2] If study is favorable select 1 of the 5 local mills which currently have available capacity for around 1000 tonnes / day & sign a contract {Likely start 1st week of the new year} January 2012. With Xmas holidays out of the way & the freeze up firmly in place, this "new year" startup date seems like a no brainer
3] Since the 43-101 + PEA will have been released by then our SP will be significantly higher We may need a small PP to raise the 1 million "up front money" to start the offsite milling process
4] It will take 3 months from the start of trucking the ore to see the money start to flow into GBB coffers
5] We will start to see monies arrive April 2013
6] Q2 / 2013 will be the end of dilution & the start of a new more agressive drill plan