RE:Worth a repost. Potential for some great news here. Also a reminder from NR of 10 November 2023
In order to preserve cash, Gowest is temporarily moving the Bradshaw mine to a "Care & Maintenance" phase, which is expected to continue until the Northern Sun tailings pond construction has been completed in or around July 2024 and when the mill is ready to begin processing Bradshaw ore.
Northern Sun started the drilling and blasting of construction rock this week. Construction is expected to begin in January 2024 and to be completed in July 2024.
Gowest is also exploring opportunities to keep funding its operational and exploration activities.
https://stockhouse.com/news/press-releases/2023/11/10/gowest-gold-provides-development-update-at-bradshaw