Floatation Plant Time lines Key milestones and timelines for the project are as follows:
- Flotation test work (February to May, 2021);
- Flotation pilot plant testing (June, 2021, onward);
- Flotation plant procurement starts (June, 2021);
- Flotation plant construction starts (late August, 2021);
- Flotation plant construction completion (April, 2022);
- Gold concentrate production commences (June, 2022
I don't recall a NR stating that construction began in August.
Its either a missed opportunity to promote by not issueing a BR or a missed opportunity to promote
because of yet another missed timeline..