RFP Schedule*
Event/Activity | Scheduled Date(s) |
BC Hydro/BCTC Registration and Interconnection Information Session (section 11) | July 8, 2008 |
Issue of Specimen EPA (section 14) | July 28, 2008 |
Submission of Registration Documents, and registration fee (section 5) | August 12, 2008 |
BCTC Interconnection Workshop | September 15, 2008 |
Proponents Submit Request to BC Hydro (for Distribution System-connected Projects) for a Preliminary Interconnection Study (section 10). | October 7, 2008 |
Proponents Submit Request to BCTC (for Transmission System-connected Projects) for a Feasibility Interconnection Study (section 10). | October 17, 2008 |
Proponents' RFP Information Session (section 11) | October 20, 2008 |
Filing of Preliminary Interconnection Study agreements with BC Hydro for Distribution System-connected Projects (4:00 p.m. PPT) (section 10) | November 7, 2008 |
Filing of Feasibility Interconnection Study agreements with BCTC for Transmission System-connected Projects (4:00 p.m. PPT) (section 10) – BASE CASE DATE | November 17, 2008 |
PROPOSAL SUBMISSION (4:00 p.m. PPT) (section 15) | November 25, 2008 |
Proponents with Projects in Fortis Service Area submit to BC Hydro a FortisBC interconnection study (section 10) | December 1, 2008 |
Post-Proposal discussions (section 17) | January through mid-April, 2009 |
Release of Feasibility Interconnection Study, Preliminary Interconnection Study, or special study (Fortis Service Area) as applicable (section 10) | February 23, 2009 |
Final Evaluation and EPA awards (section 17) | Mid-April through June, 2009 |