Join today and have your say! It’s FREE!

Become a member today, It's free!

We will not release or resell your information to third parties without your permission.
Please Try Again
{{ error }}
By providing my email, I consent to receiving investment related electronic messages from Stockhouse.

or

Sign In

Please Try Again
{{ error }}
Password Hint : {{passwordHint}}
Forgot Password?

or

Please Try Again {{ error }}

Send my password

SUCCESS
An email was sent with password retrieval instructions. Please go to the link in the email message to retrieve your password.

Become a member today, It's free!

We will not release or resell your information to third parties without your permission.
Quote  |  Bullboard  |  News  |  Opinion  |  Profile  |  Peers  |  Filings  |  Financials  |  Options  |  Price History  |  Ratios  |  Ownership  |  Insiders  |  Valuation

Evergreen Energy Inc EEE



NYSE:EEE - Post by User

Post by no1coalkingon Feb 28, 2008 12:53pm
29 Views
Post# 14564780

Clean Coal Technology A Tie Breaker:

Clean Coal Technology A Tie Breaker:Nevada Wants Cleaner Power & EEE Has The Technology ,[K-Fuel] 2 minutes ago Official: Utilities will delay applying for Ely plant OK By JOHN G. EDWARDS REVIEW-JOURNAL Nevada's electric utilities are expected to delay their application for final approval of the giant, coal-fired Ely Energy Center for two years, a top regulatory official said Wednesday. Sierra Pacific Resources said in November that it was delaying work on the Ely Energy Center for an undetermined length of time. But Kirby Lampley, director of regulatory operations for the Public Utilities Commission, said Wednesday that he didn't expect the company to file a request for final approval until late 2009 or 2010, rather than March as originally anticipated. The odds that the utilities will build the coal-fired power plant are getting slimmer with every delay, one analyst said. "I think every delay makes it less attractive from the shareholder and ratepayer perspective," said Tim Hay, a former utilities commissioner and state consumer advocate. "And the company may be forced to look at separate options (for supplying additional power)." Roberto Denis, senior vice president of Sierra Pacific Resources, rejected that perspective, though. "People who are saying that are those that are wishing it will be canceled," he said. "We don't have any information that (the Ely center) is not viable." Sierra Pacific, the holding company for Nevada Power Co. of Las Vegas and Sierra Pacific Power Co. of Reno, believes the proposed project will reduce the utilities' reliance on natural gas, a volatile and increasingly pricey fuel, Denis said. Yet, the Ely project is being put on hold because of delays in obtaining approval for use of federal land for the power plant. The Bureau of Land Management, which previously was expected to act on the utilities' request to build the project on federal land later this year, cannot meet that deadline, Denis said. The utility company has no idea when the federal agency will make its final decision on the project, Denis said. As a result, Denis said he could not project a time line for construction and completion of the first of two 750-megawatt generating units at Ely. Meanwhile, the cost of the Ely project is growing, the company said in its latest annual report. Two years ago, the company estimated the power plant and a related transmission line would cost $3.8 billion. The new report updates the estimate to $5 billion if the Ely center were built today. Escalating costs make the huge power project less attractive to Sierra Pacific stockholders and to customers of the Nevada utilities, Hay said.
<< Previous
Bullboard Posts
Next >>