RE: Drill resultsJoe;
You are correct. It will probably take 12 to 14 weeks to drill the 2F portion of the campaign with 2 machines working 24/7. That would include pad preparation, set-up, casing, drilling, testing, and tearing down. I am suprised with the increase in meterage to be drilled in the 2F phase with a jump from 3,500 meters to 6,375 meters. It'll mean a lot more information in the central portion of the property but will also represent a significant increase in monies to be spent at the same time.
Good to see an official announcement.
Cheers
Ken