MCW had previously received two containers MCW had previously received two containers of its initial plant components in late August, 2012, and this shipment is now being cleared through Houston, Texas. This container holds the remaining major components which include the rectification column, spare column parts, and spares for other system components. To minimize site development timeframes, MCW has already accumulated shovel-ready feedstock on its 1128 acre lease site near the state's main oil and gas development center of Vernal for the subsequent testing phase, which will proceed upon assembly completion.