Join today and have your say! It’s FREE!

Become a member today, It's free!

We will not release or resell your information to third parties without your permission.
Please Try Again
{{ error }}
By providing my email, I consent to receiving investment related electronic messages from Stockhouse.

or

Sign In

Please Try Again
{{ error }}
Password Hint : {{passwordHint}}
Forgot Password?

or

Please Try Again {{ error }}

Send my password

SUCCESS
An email was sent with password retrieval instructions. Please go to the link in the email message to retrieve your password.

Become a member today, It's free!

We will not release or resell your information to third parties without your permission.
Quote  |  Bullboard  |  News  |  Opinion  |  Profile  |  Peers  |  Filings  |  Financials  |  Options  |  Price History  |  Ratios  |  Ownership  |  Insiders  |  Valuation

Newcrest Mining Ltd NCMGF


Primary Symbol: A.NCM

Newcrest Mining Limited is an Australia-based mining company. The Company's principal activities are exploration, mine development, mine operations and the sale of gold and gold/copper concentrate. The Company owns and operates a portfolio of brownfields and greenfields exploration projects. The Company’s assets include Brucejack, Cadia, Havieron, Lihir, Red Chris, Telfer and Wafi-Golpu. The Brucejack asset is located approximately 950 kilometers (km) from Vancouver, Canada. The Cadia asset is located approximately 25 km from Orange, New South Wales (NSW). The Havieron asset is located approximately 45 km east of Telfer. The Lihir asset is located on the Niolam Island, approximately 900 km from Port Moresby, Papua New Guinea (PNG). The Red Chris asset is located approximately 1,700 km from Vancouver, Canada. The Telfer asset is located approximately 400 km from Port Hedland, WA. The Wafi-Golpu asset is located approximately 65 km from the city of Lae, PNG.


ASX:NCM - Post by User

Bullboard Posts
Post by panamjron Jan 09, 2013 5:30am
410 Views
Post# 20813580

News

News

 

Pretium Resources Inc.: Brucejack Project Update; Valley of the Kings Ramp Advance

VANCOUVER, BRITISH COLUMBIA--(Marketwire - Jan. 9, 2013) - Pretium Resources Inc. (TSX:PVG)(NYSE:PVG) ("Pretivm") is pleased to provide the following update on the progress of activities at its Brucejack Project in northern British Columbia.

Valley of the Kings Access Ramp

Excavation of the access ramp to the Valley of the Kings from the West Zone historical workings is now underway, with the widening of the West Zone historical workings completed. The access ramp to the Valley of the Kings from the West Zone is planned to total 546 meters in length, and is targeting the 1345 meter level at the 426600 cross-section of the Valley of the Kings. A total of 71 meters of the access ramp has been excavated since the turn towards the Valley of the Kings from the West Zone was initiated late last year. The ramp is expected to access the Valley of the Kings in April.

In addition to targeting an area of mineralization for the bulk sample, the current ramp alignment will allow acceleration of production development as it will be used to provide multiple headings for excavation of the planned production declines. A channel sampling program along the ramp will be conducted as work progresses, as the area is untested. Further underground sampling and drilling is planned after Valley of the Kings has been reached.

Bulk Sample

Strathcona Mineral Services Ltd. of Toronto has been engaged as the independent Qualified Person to oversee and report on the 10,000-tonne bulk sample from the Valley of the Kings. Excavation of the bulk sample is scheduled to begin in the second quarter. Planning is underway with Strathcona on the work required to be completed prior to excavating the bulk sample, the procedures for excavating the bulk sample and the sampling protocols.

Project Permitting

In late December, Pretivm submitted the project description for Brucejack to the British Columbia Environmental Assessment Office. The filing initiates the permitting process for the proposed 2,700 tonnes per day high-grade underground gold mine at the Valley of the Kings.

Ian I Chang, M.A.Sc., P.Eng., Vice President, Project Development, Pretium Resources Inc. is the Qualified Person (QP) responsible for Brucejack Project development.

 