Drill Time courtesy Hekios Chariot
Drill Time courtesy Hekios Chariot June 11, 2013 By
Helioschariot Chariot Oil & Gas
UPDATED – 12th June
If we presume a drill speed of 80M drill per day – as seen here
And if we agree the depth is 3670 m as announced here - with a spud date of June 1st AND a Depth from SEA Level to the spud point as pointed out to me in the comments (thanks ever so much).
Then by my calculations we are looking at 29 days to hit the first of three targets Baobaob which means approx. June 30th.
Of course the drillers might see some signs earlier in the drill process. Milton will be watching it very closely!