Management is Lying. Again.
Management is Lying. Again.Just listened to Wonnacott's Q&A from Whistler. Pure BS. Bruderheim wasn't designed for 14 trains a week. It was designed for 7 (which it still can't do). It would be impossible to get 14 trains on and off site in a week. Can't even do 10.5. Current capacity is 4.0 (the east rack is currently out of service for 3 months as we are waiting for parts). Who told Wonnacott it was ok to lie to investors? (maybe the Board? Lead by example?).