Time is just about up? Q. How long does it take to complete drilling a target drillhole?
" So we know the analysis forIMP 5 &6 have been completed about a monthThe drillrigs on our site run for a period of 24 hours each day. Drilling is completed in 12 hours shifts, in 2 shifts per day. It typically takes about two weeks to finish drilling a hole, a few days to get sampling completed, a week for sample delivery and preparation and up to three weeks for analysis."
So IMP assays probably completed over a month ago By the end of April two more holes could have been completed. From May 25 to June 17 is my time range. June 17 is the date of the annual meeting. If the results are deemed to be material they will not be held back for the annual meeting but released when available. But the meeting date does mean they will try to have something of interest for the meeting.