Look at the gold grades.
TORONTO, ON--(Marketwired - April 25, 2017) - Continental Gold Inc. (TSX: CNL) (OTCQX: CGOOF) ("Continental Gold" or the "Company") is pleased to provide an operations update and the 2017 construction outlook for its 100%-owned Buritic project located in Antioquia, Colombia. Since receiving the final environmental permit in November 2016 and securing a senior secured debt facility in January 2017 for the Buritic project, the Company has been active in ordering long lead time equipment and hiring key project personnel ahead of major earthworks beginning later this year. With the senior secured debt facility in place, the Company remains funded for its 2017 planned activities with approximately $100 million in available cash and liquidity and remains on track for first gold pour in early 2020.
Site Construction Progress
Construction of the first phase of the six-kilometre access road, which connects the Buritic property entrance to the future plant and infrastructure site in the Higabra valley, is now complete (Figures 1, 2 and 3). The road, which was built on time and budget, is now being used for transportation of construction personnel and equipment and for related activities. The second phase of the access road, which will upgrade the road to accommodate plant and infrastructure equipment deliveries, has commenced and is expected to be completed in Q4 2017.
The Company is well advanced in the installation of several modular office buildings, which will serve to support project and mine development activities (Figure 4). The buildings are located near the Rampa Sur portal and are expected to be completed in Q3 2017. In addition, clear-cutting of future plant and infrastructure sites in the Higabra Valley is approximately 55% complete and is expected to be completed in Q3 2017.
The Company anticipates mobilization of earth moving equipment to the Higabra valley shortly; site excavation is scheduled to begin in Q3 2017, followed by the initial concrete pours in Q4 2017. Both activities are anticipated to be sufficiently completed by the end of Q2 2018 to allow initial structural steel installations to commence.
Mining Activities 2017
Two mechanized long-hole stopes, each measuring approximately 25 metres along strike by 15 metres high, will be mined in sequence to extract nearly 30 metres vertically in the Hanging Wall vein. Extraction of these stopes is anticipated to commence in the third quarter of 2017. In 2016, the Company successfully extracted two side-by-side mechanized long-hole stopes, which encountered approximately twice the gold grade and extracted approximately twice the ounces of gold when reconciled with the NI 43-101 mineral resource model; results are summarized in the following table.
The extraction of additional trial mining stopes in 2017 and additional long-hole stopes planned during the construction phase will serve as excellent training for Company personnel, while providing valuable reserve reconciliation data with actual mining results. The location of the trial mining stopes within the Yaragu vein system and related associated information will be announced once planning has been completed towards the end of Q2 2017.
Procurement
The Company has been diligently working on procuring all long lead time equipment with the goal of having purchase orders placed prior to the end of Q3 2017. To date, the Company has ordered the following long lead time items:
The Company expects 30% of the underground mine development equipment to be delivered in the third quarter of 2017 (Figure 5). As equipment arrives, underground development activities will begin to ramp-up approximately six months ahead of schedule.
Engineering and Project Management
As announced on April 3, 2017, the Company awarded the Buritic project contract for construction management to Merit Consultants International Inc. and the contract for engineering and procurement to M3 Engineering & Technology Corp. The construction management team members are currently being integrated into the project team and detailed engineering is ongoing.
Infill and Exploration Drilling
The Company plans to resume exploration drilling with a minimum 12,000-metre drill program commencing in the second quarter of 2017. Details of the program will be announced shortly.
"After years of advancing and de-risking the project, the time has finally arrived to begin constructing the first modern large-scale gold mine in Colombia. The Company anticipates the construction phase to provide meaningful employment opportunities for individuals within our area of influence, while adhering to strict international standards," commented Ari Sussman, CEO of Continental Gold. "We are also very excited to resume drilling at Buritic for the first time in two years and remain confident that not only should deposits continue to grow, but we expect to uphold the trend of increasing precious metal grades and mineable widths with denser drill spacing and sampling."
"We are very pleased with our progress in ramping up project activities so quickly," added Don Gray, COO of Continental Gold. "Our crews are rapidly adapting to mechanized development and we expect our plans for additional long-hole trial mining to add to their mining skills as well as increase understanding of our high-grade vein systems. Engineering and procurement activities are advancing very quickly and our schedule for beginning construction remains on track. We also remain on course to achieve our early 2020 production goal."
About Continental Gold
Continental Gold Inc. is an advanced-stage exploration and development company with an extensive portfolio of 100%-owned gold projects in Colombia. Formed in April 2007, the Company -- led by an international management team with a successful track record of discovering and developing large high-grade gold deposits in Latin America -- is focused on advancing its high-grade Buritic gold project to production.
For information on the Buritic project, please refer to the technical report, prepared in accordance with NI 43-101, entitled "Buritic Project NI 43-101 Technical Report Feasibility Study, Antioquia, Colombia" and dated March 29, 2016 with an effective date of February 24, 2016, led by independent consultants JDS Energy & Mining Inc. The technical report is available on SEDAR at www.sedar.com, on the OTCQX at www.otcmarkets.com and on the Company website at www.continentalgold.com. Additional details on Continental Gold's suite of gold exploration properties are also available at www.continentalgold.com.