Woodrush project -- timeline
Woodrush project -- timeline Woodrush project -- timeline
A permit application for the Woodrush drilling program and the related pad and road construction was filed with the appropriate regulatory authorities on Jan. 16, 2018. The application requires a minimum 15-day turnaround. Accordingly, the company expects to receive its licence in the very near term. In preparation for the first well spud, anticipated in mid-February, 2018, DXI has completed the following key preparation steps