Hudson Resources Inc. ("Hudson" or the "Company") (TSXV:HUD) (OTC:HUDRF) is pleased to provide an update on construction activities at the Company's 100% owned anorthosite (calcium feldspar) mine in Greenland. Hudson recommenced construction in April, completing the accommodation complex and the truck shop shortly thereafter. The Company is currently completing the mechanical and internal steel installation on the process plant. Hudson plans on shipping processed anorthosite from the site by the end of the year.
Construction highlights for 2018 include:
-- Process plant internal steel and mechanical installation is 70% complete
-- Ore storage building steel erection is set to commence in one week and is scheduled to take 10 weeks to complete
-- All major process equipment and steel now on site
-- Construction completed on the truck shop and accommodation complex
-- Port facility has received four ships this year delivering over 400 tonnes of steel, equipment and construction supplies
-- Currently 38 construction personnel on site which will peak at 44 in August
James Tuer, Hudson's President, stated: "We are very pleased with the excellent progress of our construction team. So far, we are on target to start commissioning in October with the objective of getting our first shipment of product out before the end of the year."
After soliciting bids from Greenland, Europe and North America, Ironclad Metals Inc. of British Columbia was awarded the contract for steel and mechanical erection for the process plant, ore storage building and material handling facilities. Ironclad is one of North America's leading companies for structural steel and mine construction. Ironclad is supported by the Gisborne group who specialize in mechanical installation of mining projects.
The electrical installation contract was awarded to Lillegaarden EL of Denmark. Lillegaarden have executed several industrial projects in Greenland and will commence electrical installations in early August. Merit Consultants International of Vancouver continues to provide construction management expertise to the project.
Hudson recently completed an $18 million equity financing in order to complete construction and fund working capital and debt payments.
Pictures of the construction progress can be found on the company website at https://hudsonresourcesinc.com/gallery.
ON BEHALF OF THE BOARD OF DIRECTORS
"James Tuer"