jeschemon Nov 03, 2019 9:57am
124 Views
Post# 30302095
Re Contact management
Re Contact management
SeekingAU Its good your going to be there.
The major questions should focus on the paste plant and the ventilation because those two issues present the bottlenecks to mine operations.
Drill down on those two issues. What are they doing to fix the paste plant. What is the critical component they need to install. Are they working on that now or is this a component that has not arrived yet. If it has not arrived what is the lead time to get it on site. They said the plant should be repaired by Dec. Now is that early Dec. or late Dec.
On the ventilation Harte said in a previous update that this issue was resolved. So what is the problem now with it. Has the problem been fixed or are they still working on that.
There was no mention of drills operating. I thought they said a drill was going to be mobilized in early Oct. What are their drilling plans.
Last winter they had operational problems because of the cold weather. Have they fixed this problem. If so I'd like to know how.
Please Seekingau keep us posted.
Do these delays necessitate more financing. If so - how much? If so- what are their plans to get it? Bank? Equity ?