RE:RE:RE:RE:Good finish on good volume.Patience.
It tooks Tesla from 2014 to 2019 to keep just at approx USD 40,00... FCC is within time shedule.
Extracted from FCC's ddt. 24th September 2020:
This in turn, has delayed the commencement of the continuous pilot plant, which will be underway in the coming weeks in consultation with the Joint Technical Committee. The
pilot plant test work is expected to be completed in Q4 2020. Next Steps
The Company expects to continue to advance and de-risk the Project by pursuing the following activities:
- Complete all technical optimization programs, with assistance from Glencore’s technical team
- Complete continuous pilot plant test work on the leaching and solvent extraction circuits and produce battery grade cobalt sulfate product
- Submit the required permit amendments to operate at the expanded 55 TPD throughput rate
- Continue to pursue opportunities to further reduce operating costs
Upon completing the activities noted above, a commercial contract and financing package will be finalized prior to a formal construction decision. The financing process, being led by CIBC, has progressed to phase 2. The Company received numerous initial proposals to fund the refinery capital costs and has now selected several of these to move to the next phase of due diligence.
...
We have to await for finalizing the pilot plant test work which will be flanked with closing of financing contracts.
I think we are on the road...