RE:RE:RE:RE:https://www.northernontariobusiness.com/regional-news/far-noThe bulk of the construction is the removal of trees which has to be completed while the muskeg is frozen solid. This will be done using D-8's or 9's. This has to be completed by June in order to start dumping fill across the road right of way pushing it forward mile upon mile. The bridges will be constructed along the way.