RE:still waiting ...politicat wrote: I am frustrated with the lack of anticipation of a torch order --- even 1 torch.
When asked how long it will take to get it out the door -- even now, 7 weeks after the order came in, the response is the standard 2 weeks to 4 months from receipt of contract. Peter says, because of items with long lead times, a large touch order would be towards 2 weeks and a small order ( like maybe an order of 1 torch ?) would be towards 4 months.
The company stock price goes parabolic based on potential torch sales and, after several months of negotiations, when Client A finally ageees to buy they do not have a torch ready to go?
Not one ?
Knowing that it will take 3 months to get one made --- not one.
Peter said they had recieved the Client A order 1 or 2 months before PYR signed it back ... and yet not one torch was made.
Knowing the long lead time items are an issue they could have pre-ordered just those items.
PYR is very fortunate to have a patent on pelletization. If i was Vale and it took 2 months to get a small contract signed and another 3 months to make 1 touch i would be looking elsewhere.
yikes...
Guess it's a good thing that you don't work for Vale, and you instead bring your talents to complain on public forums. lol.