RE:New presentationTo add to what I posted earlier, here are some comparisons I made with the April presentation ie what was done in Q2:
#1 the Drilled and completed wells went from 5 to 12 ie +7. 7 is the # of wells going on line in August.
(the 2 Charlie Lake wells were completed and are going online in August, the 3 Pouce Coupe wells were drilled and completed and are going online in August, and 2 wells at Wembley were completed and 2 wells are going on line at Wembley in August (I didn't check if its the same 2 wells that were completed in Q2).
#2 The $30M capex increase is $24M infrastructure and $6M Drill and complete (1 Wembley drill and 1 Wembley completion added - nothing else has changed).
#3 The 2nd half drilling & completion program consists of completing 8 Oak wells (and bringing 10 online in Q4), plus drilling 4 wells at Wembley and completing 2 of them.
#4 At present, at Wembley Kelt will end 2021 with 5 wells drilled and completed and 3 wells drilled uncompleted. Which means that assuming no further changes, Kelt will have brought online 2 Wembley wells in 2021...