New PlantDry commissioning of the new flotation plant and associated equipment is scheduled to start from June 1st, 2022 onwards. The CIL plant will continue operation until June 30th, 2022. Tie-in and wet commissioning of the flotation plant will commence on July 1st, 2022 and continue to July 14th, 2022. Ore commissioning is expected to start on July 15th, 2022. The gold remaining in circuit will be recovered by emptying the leach and CIL tanks of slurry and bagging the harvested carbon for subsequent elution. The elution circuit will continue to operate for around a month after the CIL plant shutdown.