RE:What's up with Trans Mountain Pipeline? (off topic)The cost is now $21.4 billion,. Original estimate was $12.6 billion. Floods and pandemic to blame. The Federal Gov't says it wil not put more money into the project.
Like giant dams, Site C original cost $7.9 billion, now $16 billion.
Muskrat Falls, original cost $6.2 billion now $12.7 billion.
First Nations affected by the Trans Mountain project have a chance to buy 100%. But what will be the final price?
Coastal Gaslink, original estimate $6.6 billion, now $10 billion.
Might as well double the cost estimate to get the final cost\, that's the pattern.
Anyway, a pipe shipment just left the steel mill this morning via CN train, heading for one of these projects.