RE:Congratulations again ... total of C$5.9 million in 2 daysI was curious what the Aurora/AXE collaboration aiming at :
20 tonnes per day H2?
10MW power levels ?
might mean, or equivalent to, for comparision / knowledge sake.
So 7,300 tonnes H2/year = 20 tonnes H2/d x 365 days
For reference SU, one of several Alberta upgraders, talk 300,000 tonnes / year H2 for their own demand.
Google grabbed for me in this article a Shell 10MW H2 project :
https://www.reuters.com/business/energy/shell-opens-10-mw-german-hydrogen-electrolyser-boost-green-fuel-output-2021-07-02/ July 2, 2021 10:44 AM MDTLast Updated 2 years ago
Shell opens 10 MW German hydrogen electrolyser to boost green fuel output
FRANKFURT, July 2 (Reuters) - Royal Dutch Shell (RDSa.L) on Friday launched Europe's biggest hydrogen electrolysis plant at the Wesseling site of its Rheinland refinery after two years of construction, as it expands further into alternative energies.
The Refhyne plant, with a 10 megawatt (MW) capacity, will produce green fuels as part of a European Union-funded consortium which is already setting its sights on a 100 MW facility at the site near Cologne.
The Refhyne polymer electrolyte membrane (PEM) electrolyser will produce up to 1,300 tonnes a year of green hydrogen. The plant cost around 20 million euros ($23.72 million) of which half came from EU funds.
Only 1,300 tonnes/year vs 7,300
...
And the price zinger that Shell appear happy to pay 5x what grey or turquios H2
Fabian Ziegler, CEO of Shell in Germany, noted that green hydrogen was still five times the price of fossil hydrogen, but said this could be reduced by half through scale and efficient supply chains, with the rest to be offset via policy interventions around renewable support and carbon prices.