Join today and have your say! It’s FREE!

Become a member today, It's free!

We will not release or resell your information to third parties without your permission.
Please Try Again
{{ error }}
By providing my email, I consent to receiving investment related electronic messages from Stockhouse.

or

Sign In

Please Try Again
{{ error }}
Password Hint : {{passwordHint}}
Forgot Password?

or

Please Try Again {{ error }}

Send my password

SUCCESS
An email was sent with password retrieval instructions. Please go to the link in the email message to retrieve your password.

Become a member today, It's free!

We will not release or resell your information to third parties without your permission.

Almonty Industries Inc T.AII

Alternate Symbol(s):  ALMTF

Almonty Industries Inc. is a Canada-based company, which is engaged in the mining, processing and shipping of tungsten concentrate, as well as the exploration and evaluation of its projects. The Company operates through four segments: Los Santos Mine, Panasquiera Mine, Valtreixal Project, and Woulfe. The Los Santos Mine is located in Spain whose operations relate to the exploration and mining of Tungsten. The Panasqueira Mine is located in Covilha Castelo Branco, Portugal, whose operations relate to the exploration and mining of tungsten, as well as the production of copper and tin concentrate by-products. The Valtreixal Project is located in Spain whose operations relate to the exploration and evaluation activities of the Valtreixal tin/tungsten project. Woulfe’s properties are located in Gangwon Province, Republic of Korea. The Woulfe's operations relate primarily to the exploration, evaluation and development of the Sangdong Project.


TSX:AII - Post by User

Post by 1dollarinto2on May 02, 2023 11:50pm
218 Views
Post# 35426658

Construction at Sangdong

Construction at SangdongI couldn't be much happier with the most recent update from Almonty. The highlights for me are:

1. "The final drive is now expected to arrive in May 2023." - this suggests the shipping time was on the shorter end of the range Lewis mentioned at the last IIF.

2. 99% of the long lead time equipment already arrived and 75% of the short lead time equipment will be loaded for transport in May. Lewis can confirm the ship time for the short lead equipment on the May 10th IIF, I expect it to be two months or less.

3. The the new 4 MW power system is real, tangible, construction progress with pictures, same with the pictures of surcace scalping.

With construction acutally underway I am looking forward to Lewis providing an updated timline for starting production at the May 10th IIF. I am thinking the reason Almonty didn't update their investor presentation after the last IIF was because the timlines were only estimates until the ship date was confirmed. Now that the ship dates are confirmed I expect we will have an updated presentation soon with a very accurate estimation of production starting.

An updated presentation fits with the comment from Lewis about letting the wider investing market know all about Almonty.

Is anyone planning on asking questions during the IIF presentation? If so, what are you curious about?