RE:RE:RE:RE:RE:RE:RE:RE:RE:Should be a good thing"we need weekly volume of 1 million shares or more"......
IMO, this won't happen until these catalysts occur-
1.Partnership is announced and
2.Osmose purchases PP. ($3.55M Cdn)
When the Elaborate is reviewed, passed & awarded a C of R-
3.Metallurgy results on Piskanja are released by lab to BONE.
4.Part 2 -FS is submitted to Ministry.
5.Tranche 1 funding is paid by Osmose 30 days afer FS approved(10M Euros)
6.Then Institution(s) commit to & steer project pricing runup.
7.Multiple off-take Agreements are announced, share price continues to run up.
8.Mining license is granted.
9.Part 3 Blue Prints for mine initiated/completed by an Engineering firm contractor.
10. Tranche 2 funding is paid by Osmose 30 days after Part 3 completed(12M Euros).
11. Mine construction commences by our Partnership, or a Major who buys us out.
TD states everything completed this year.
Note - approaching 6 months since LOI was prepared with Osmose, which is the same about of time consumed by Temas Resources to announce their Partnership with Erin Ventures.