Largest In-Depth TURNAROUND In MEG's History
- cost: $ 66 million
from Q2/2023 CC: COO:
- 220,000 man-hours of labor utilized
- BOP PENALTY in LOST production of 20,000 bbls/d for Q2/2023
- did NOT complete ALL the WELL TIE-INS during major turnaround due to SUPPLY CHAIN ISSUES
- since these tie-ins will be done in Q3/2023, there will be REDUCED BOP due to CUTTING OFF STEAM to perform these tie-ins
- there is a SHORTAGE of QUALIFIED CONTRACT WORKERS and invoice inflation on this manpower is double digits