Detailed engineeringIn the last interview with Eric Zaunscherb he specifically said ( at the 2.00 minute mark ) the detailed engineering had to be 60 to 65% complete before doing a final investment decision.
Unless I missed it, we did not get a NR or other feedback on the engineering progress.
I think we should contact management to see what is going on with engineering ???
The other items for the so called "Final Investment Decision" are the long lead equipment like the transformers that have been ordered already and of course the long awaited "financing package".
He does mention that there will be no tree cutting before that decision.
So now I am waiting for two NR's. The engineering advancement and the financing package.
The tree cutting is not relevant.