RE:RE:capitulationManagerment need to get a sales agreement(s) in place asap. IACX will not committ funds to build the HRU if they aren't confident that Avanti can actually sell the production for a reasonable price. If they still plan on starting production by end of Q3/early Q4, IACX will have to ship the modules to the site by mid-August to begin the assembly and allow for testing/commissioning. Two months since announcing the agreement with Edelgas and nothing to report, what gives?
I emailed investor relations more than 2 weeks ago and asked if they could confirm if IACX had started fabricating the HRU modules, crickets chirping. No response. One can only assume that IACX has done nothing at this point and will not start fabrication until there are signed sales agreements in place to their liking.