Lookout or Outlook? Status w IMII and Phase III Potash dryi
From 2024Q2 MD&A
Notice the past tense used.
The Company has completed construction and testing of a 100 kilogram per hour potash ore drying system. The findings were presented to IMII in July, 2024. As of this MD&A, a proposal for Phase 3 has been presented to IMII and is currently under review. Phase 3 of the project would include the design, construction and testing of a larger shop-scale demonstration dryer.
From IMII website
Proponent: Acceleware
Project Duration: April to June 2024
Project Cost: $322,152
Industry Contribution: $322,152