10,000 tonne bulk sample in the future
The work described in the application includes dewatering of the mine by shaft no.1 to an approximate depth of 300 metres, driving of a 1,429-metre ramp from surface to connect to level 750' of the mine, rehabilitation of drifts and crosscuts accessible from the shaft, excavation of 2,000 metres of drifts, crosscuts and some 20 drill bays, diamond drilling and
the extraction of a 10,000-tonne bulk sample from veins 14 and/or 16 and/or some other structure to be identified by drilling.