BMO re Q3 Production - Kipushu
Work programs are underway to resolve the ramp-up issues and, in addition, the debottlenecking program of the Kipushi concentrator is ongoing, with engineering and procurement of long lead items underway. As a reminder, the debottlenecking program aims to increase yearly concentrator processing capacity by 20% to 960,000t and is expected to be completed in mid-2025.
Comment by
BSdetector2016 on Oct 07, 2024 2:15pm
Normal bugs at the start of any mining operation.