Management has been telling us to anticipate the hot commissioning of the Enel system (our first and only battery sale to date) in Q3-23. September is the last month of Q3. So I dare to expect a NR on this subject in the next 2 weeks. Hoping that it will have a positive impact on the sp. Q2-23 CC Transcript
Francesco D'Alessio - President of LCE: I'm also happy to highlight that the system was interconnected to the grid and the system inverter was effectively utilized to form the chemistry during the quarter. As of now, the battery is undergoing charge discharge cycles as part of the hot commissioning phase, which we're diligently working to conclude in the third quarter of 2023. This phase, along with the anticipated provisional acceptance of the Enel system represents a substantial step forward in the realization of our collaborative efforts.