VANCOUVER, Nov. 9, 2016 /PRNewswire/ - Alexco Resource
Corp. (NYSE‑MKT:AXU, TSX:AXR) today reports financial results for the quarter ended September
30, 2016. All figures are expressed in Canadian dollars unless otherwise stated. For the third quarter of 2016
Alexco recorded a net loss of $640,000 or $0.01 per share, including
$0.9 million in depreciation expense, share-based compensation expense and an unrealized loss on
warrants held offset by a realized gain of $1.3 million on the disposal of shares held as an
investment. Alexco Environmental Group ("AEG"), a wholly owned subsidiary of Alexco, recognized revenues of $3.2 million during the third quarter of 2016 with a gross profit of $0.7
million, achieving a gross margin of 22%.
Third Quarter Highlights
- Improving and strong unrestricted cash position with cash and cash equivalents at September 30,
2016 of $23.0 million and net working capital of $25.0
million compared to $8.2 million and $12.6 million,
respectively, at December 31, 2015.
- At the end of October the Company completed its 2016 Bermingham diamond drill program with 50 holes for a total of 17,300
meters ("m"). Interim drill results released on September 13, 2016 outlined a zone of high grade
mineralization beginning approximately 150m from surface and extending down plunge approximately 250m including an intercept of
7.5m true width of 2,715 grams per tonne ("g/t") (87.3 ounces per tonne ("oz/t")) silver (including 2.4m (true width) of 6,391
g/t (205.5 oz/t) silver within the zone of down-plunge extension. Final results from the Bermingham program are expected to be
available in the fourth quarter.
- 3,267,075 warrants were exercised for proceeds of $4.6 million.
- The Company sold investments in marketable securities for proceeds of $1.5 million for a gain
of $1.3 million.
- A performance bond was released to Alexco in the amount of $3.8 million (US$2.9 million) related to the AEG's Globeville Smelter Project in Denver
Colorado.
- As of September 30, 2016 the Company has spent all of the $3,001,125 flow-through funds raised.
Alexco's President and Chief Executive Officer Clynt Nauman said, "In the third quarter,
following the release of encouraging interim results in September, we expanded our Bermingham surface drill program from 8,000 to
17,000 meters. Elsewhere at Keno Hill we continued with a mill assessment and maintenance program and installation of the Flame
& Moth underground portal and drove the first 20 meters of the production ramp. Pending the final results of the Bermingham
drill program, release of an updated Preliminary Economic Assessment and continued strength in the silver market, we will be well
positioned by year end to consider redevelopment at Keno Hill."
Summary Financial Results and Information
|
|
|
|
|
|
|
|
(expressed in thousands of dollars, except per share amounts)
|
Three Months Ended
September 30
|
|
Nine Months Ended
September 30
|
|
2016
|
2015
|
|
2016
|
2015
|
|
|
|
|
|
|
Environmental services revenue
|
3,243
|
3,408
|
|
8,422
|
10,534
|
|
|
|
|
|
|
Gross profit from environmental services
|
710
|
869
|
|
1,985
|
2,640
|
|
|
|
|
|
|
Loss before taxes
|
(246)
|
(1,986)
|
|
(2,388)
|
(4,851)
|
Net loss
|
(640)
|
(1,649)
|
|
(2,598)
|
(4,007)
|
Total comprehensive loss
|
(1,819)
|
(1,834)
|
|
(2,218)
|
(4,498)
|
Loss per share – basic and diluted
|
($0.01)
|
($0.02)
|
|
($0.03)
|
($0.06)
|
Cash flows consumed from operating activities
|
(492)
|
(1,483)
|
|
(3,452)
|
(3,486)
|
Keno Hill Exploration
The Company has completed an exploration program of 50 drill holes totalling 17,300m of surface diamond drilling to follow up
on prior identification of high grade silver results at the Bermingham prospect. Approximately $3.3
million was invested in the expanded exploration program, the majority funded by way of a $3
million flow-through financing in December 2015. The surface drilling program, initiated
with two drills and later expanded to three diamond drills, commenced in June and completed in late October. The Company is
expending additional funds to gather important geotechnical and hydrogeological information, as well as undertaking a preliminary
metallurgical program to test the Bermingham mineralization. Interim drill results on 18 drill holes were released on
September 13, 2016 (see September 13, 2016 press release entitled
"Alexco Confirms, Expands High Grade Silver Zone at Bermingham Deposit; Drilling Continues") and final results are expected to be
available in the fourth quarter.
Initial assay results confirmed and expanded the Bermingham high grade zone (the "Bear Zone"), including a recent intercept of
7.5m true width of 2,715 g/t (87.3 oz/t) silver (including 2.4m (true width) of 6,391 g/t (205.5 oz/t) silver) from hole
K-16-0608 drilled approximately 100m down plunge from the deepest intercept reported in 2015. Overall, all other composite
intercepts in the high grade Bear Zone now range between 504 g/t to 7,462 g/t silver over composited true thicknesses ranging
from 1.3m to 6.4m.
The drill objectives at Bermingham were firstly to increase confidence, most notably to infill and expand the previously
identified zone of high grade silver intercepts on the Bear Vein with sufficient density to permit resource estimation; and
secondly, to explore up and down plunge of the high grade zone for possible extensions to other favourable structural and
stratigraphic positions in which additional mineral deposition may have occurred.
Keno Hill Silver District PEA
The Company plans to provide an updated National Instrument 43-101 compliant Preliminary Economic Assessment ("PEA") for its
100% owned KHSD in the fourth quarter of 2016 which will incorporate the re-engineering and optimization of the mine plan along
with an updated mineral resource estimate for the Bermingham deposit.
The Company expects a Water Use Licence amendment hearing to occur in the first quarter of 2017, which is the final remaining
permit required to commence mining operations at the Flame & Moth deposit.
Keno Hill Development Update
The Company continued with mill assessment and maintenance programs during the quarter. Mechanical assessment and maintenance
of equipment is part of the routine process of maintaining the crushing and milling equipment assets in a condition where
resumption of processing operations can be initiated if warranted.
In October the Company completed installation of the underground portal and infrastructure at the Flame & Moth deposit and
drove the first 20 meters of the production ramp. This will allow resumption of development activities to begin at full scale in
the future. This ramp will ultimately be driven to the upper production levels of the Flame & Moth silver deposit.
As a result of the Company filing an updated Reclamation and Closure Plan for its current operations and the future
development of the Flame & Moth deposit, the Quartz Mining License ("QML") required that Alexco increase its posted security
from $4.2 million to $6.3 million. On July 26,
2016 the Corporation posted the additional $2.1 million in cash for security and are
currently working with the Yukon Government to substitute a portion of the cash posted in exchange for a pledge of assets.
Alexco Environmental Group
AEG recorded revenues of $3.2 million and a gross profit of $0.7
million, compared to revenue of $3.4 million and a gross profit of $0.9 million in the third quarter of 2016. The decrease in gross profit from the prior period is mainly
attributed to unanticipated project related costs in the US as well as costs associated with obtaining the release of the
Globeville Smelter Project performance bond.
At the Gold King Project in southern Colorado, the US Environmental Protection Agency authorized an expansion of the plant to
approximately double the treatment capacity of the Interim Water Treatment Plant. Construction related to this and further
upgrades are currently underway.
On the Globeville Smelter Project, a Completion Report, which documents the work completed at the site and the monitoring
results, was submitted to the State of Colorado in July. The Completion Report triggered the
release of $3.8 million to AEG with the remaining $0.5 million to
stay in the performance bond for approximately 2 years.
Financial
Alexco's cash and cash equivalents at September 30, 2016 totaled $23.0
million compared to $8.2 million at December 31, 2015, while
net working capital totaled $25.0 million compared to $12.6 million
for the same dates. With its cash resources and net working capital on hand at September 30,
2016, Alexco anticipates it will have sufficient capital resources to carry out all of its currently-anticipated
exploration programs, environmental services business and corporate offices and administration as planned for 2016 and 2017.
Financial Report and Conference Call for Third Quarter 2016
Full details of the financial and operating results for the second quarter ended September 30,
2016 are described in Alexco's interim condensed consolidated financial statements with accompanying notes and related
Management's Discussion and Analysis. These documents and additional information on Alexco, including its annual
information form, are available on the Company's website at www.alexcoresource.com and on SEDAR at www.sedar.com and on EDGAR at www.sec.gov/edgar.shtml.
Alexco is holding an audio webcast conference call to discuss these results at 11:00a.m. Eastern
(8:00 a.m. Pacific) on Thursday, November 10, 2016. To
participate in the live call, please use one of the following methods:
Dial toll free from Canada or the US:
|
1-866-233-4606
|
Dial from outside Canada or the US:
|
1-416-640-5946
|
Conference ID#:
|
1253898
|
Live audio webcast:
|
www.alexcoresource.com
|
Participants should connect five to ten minutes before the call.
The conference call will be recorded, and an archived audio webcast will be available at www.alexcoresource.com. Through November 24, 2016, a replay of the call will be available by telephone at the following:
Dial toll free from Canada or the US:
|
1-888-203-1112
|
Dial from outside Canada or the US:
|
1-647-436-0148
|
Replay Passcodes:
|
Conference ID # 1253898
|
Qualified Persons
The disclosure in this news release of scientific and technical information regarding exploration projects on Alexco's mineral
properties has been reviewed and approved by Alan McOnie, FAusIMM, Vice President, Exploration,
while that regarding mine development and operations has been reviewed and approved by Scott
Smith, P.Eng., former Bellekeno Mine Manager, both of whom are Qualified Persons as defined by National Instrument 43-101
‑ Standards of Disclosure for Mineral Projects.
About Alexco
Alexco Resource Corp. owns substantially all of the historical Keno Hill Silver District located in Canada's Yukon Territory, including the Bellekeno silver mine, the Flame
& Moth, Lucky Queen, Bermingham and Onek deposits, and other historic and surface resources within the district. Bellekeno,
which commenced commercial production at the beginning of calendar year 2011, was Canada's only
operating primary silver mine from 2011 to 2013. Alexco is currently undergoing an interim suspension of operations at Keno Hill
in order to decrease costs and reposition the district for long-term, sustainable operations. Between 1921 and 1988, the Keno
Hill Silver District was a world-class silver producer, with more than 217 million ounces of silver produced at average grades of
40.5 ounces per ton silver, 5.6% lead and 3.1% zinc (Yukon Government's Minfile database). These historical production grades
would rank Keno Hill in the top 3% by grade of today's global silver producers. Employing a unique business model, Alexco also
provides mine-related environmental services, remediation technologies and reclamation and mine closure services to both
government and industry clients through the Alexco Environmental Group, its wholly-owned environmental services division.
Please visit the Alexco website at www.alexcoresource.com
Certain statements ("forward-looking statements") in this news release contain forward-looking information concerning the
Company's anticipated results and developments in the Company's operations in future periods, planned exploration and development
of its properties, plans related to its business and other matters that may occur in the future, made as of the date of this news
release. Forward-looking statements may include, but are not limited to, statements with respect to the future remediation
and reclamation activities, future mineral exploration, the estimation of mineral reserves and mineral resources, the realization
of mineral reserve and mineral resource estimates, future mine construction and development activities, future mine operation and
production, the timing of activities and reports, the amount of estimated revenues and expenses, the success of exploration
activities, permitting time lines, requirements for additional capital and sources and uses of funds. Forward-looking
statements are subject to a variety of known and unknown risks, uncertainties and other factors which could cause actual events
or results to differ from those expressed or implied by the forward-looking statements. Such factors include, among others,
risks related to actual results and timing of exploration and development activities; actual results and timing of mining
activities; actual results and timing of environmental services activities; actual results and timing of remediation and
reclamation activities; conclusions of economic evaluations; changes in project parameters as plans continue to be refined;
future prices of silver, gold, lead, zinc and other commodities; possible variations in mineable resources, grade or recovery
rates; failure of plant, equipment or processes to operate as anticipated; accidents, labour disputes and other risks of the
mining industry; First Nation rights and title; continued capitalization and commercial viability; global economic conditions;
competition; and delays in obtaining governmental approvals or financing or in the completion of development activities.
Forward-looking statements are based on certain assumptions that management believes are reasonable at the time they are
made. In making the forward-looking statements included in this news release, the Company has applied several material
assumptions, including, but not limited to, the assumption that the Company will be able to raise additional capital as
necessary, that the proposed exploration and development will proceed as planned, and that market fundamentals will result in
sustained silver, gold, lead and zinc demand and prices. There can be no assurance that forward-looking statements will
prove to be accurate and actual results and future events could differ materially from those anticipated in such
statements. The Company expressly disclaims any intention or obligation to update or revise any forward-looking statements
whether as a result of new information, future events or otherwise, except as otherwise required by applicable securities
legislation.