- Pre-tax: NPV5% of $299 million and 36% IRR with a 1.6-year payback period - After-tax: NPV5% of $169 million and 24% IRR with
a 2.3-year payback period - Production averages 79,000 oz. of gold and 32 Mlbs of copper over a 10-year mine life - Life of mine
("LOM") average cash cost of $313/oz. gold and LOM average cash cost plus sustaining cost of $396/oz. gold (net of copper and
silver by-product credits) - Initial capital costs estimated at $214 million with a 2-year pre-production period - LOM sustaining
and closure capital costs estimated at $87 million - Base case metals prices: $1,250/oz. for gold, $2.50/lb for copper, $18.00/oz.
for silver
VANCOUVER, BRITISH COLUMBIA--(Marketwired - Jan. 18, 2017) - Geologix Explorations Inc. (TSX
VENTURE:GIX)(FRANKFURT:GF6)(BERLIN:GF6)(STUT:GF6)(MUN:GF6)("Geologix" or "the Company") is pleased to announce the results of a
positive, independent Preliminary Economic Assessment ("PEA") on its 100% owned Tepal Gold/Copper Project ("Tepal" or the
"Project") located in southwest Mexico. All currency values are in U.S. dollars unless otherwise indicated.
The PEA supports Tepal's robust economic potential as an open pit operation using contract mining. Sulphides will
be milled and processed via a 22,000 tonnes per day ("tpd") copper, gold and silver ("Cu/Au/Ag") flotation concentrate circuit
combined with a secondary carbon-in-leach ("CIL") circuit producing gold and silver ("Au/Ag") doré. Oxides will be milled and
processed via a separate 5,500 tpd CIL circuit producing Au/Ag doré.
"Achieving this milestone is a critical first step toward rewarding the long-term dedication and perseverance of
all of our key stakeholders," said Kiran Patankar, Geologix's President and Chief Executive Officer. "During a challenging
multi-year period for junior miners following the completion of a Pre-Feasibility Study on Tepal in 2013, our Board of Directors
made a prudent decision to curtail spending and minimize shareholder dilution, while stepping in to provide the Company with
interim funding to keep the Project in a clean and unencumbered condition until resource capital markets improved. When metals
prices stabilized and reversed direction in 2016, the Company enhanced its management team, completed a modest private placement,
and commenced an extensive review of Tepal. We look forward to resuming project development based on these promising
results."
"The optimized PEA design presents a low-capex, high-margin development scenario that maximizes economic return at
today's metals prices while retaining significant optionality and upside should prices continue to improve. With a 10-year mine
life, average annual gold production of 79,000 oz., LOM average cash cost plus sustaining cost of $396/oz. (net of copper and
silver by-product credits), manageable initial capital cost of $214 million, extensive historical technical and permitting work
already completed, and strong local community support, we believe Tepal is in the top quartile of porphyry gold/copper
development projects. We intend to further optimize and de-risk Tepal by progressing toward a Feasibility Study, while
maintaining a disciplined spending approach that maximizes value for our shareholders."
In August of 2016, Geologix commissioned JDS Energy & Mining Inc. ("JDS") to complete the PEA, which involved
evaluating design input parameters and mineral processing requirements, performing mining and processing optimizations and
trade-off studies, estimating facilities, infrastructure and operating costs, and generating project economics associated with
the potential development of the Tepal mineral resource. A technical report will be filed on SEDAR (www.sedar.com) and the Company's website (www.geologix.ca) within 45 days.
The PEA is preliminary in nature and includes inferred mineral resources considered too speculative geologically to
have the economic considerations applied that would enable them to be categorized as mineral reserves. Mineral resources that are
not mineral reserves do not have demonstrated economic viability. There is no certainty that the PEA will be realized.
Project Design and Economics
A summary of the PEA operating assumptions using metals prices of $1,250/oz. gold, $2.50/lb copper and $18.00/oz.
silver ($1,250/oz. gold, $2.25/lb copper and $20.00/oz. silver for pit design) is as follows:
Operating Assumptions/Highlights |
(Currency in USD) |
Mine Life |
9.8 years |
Total Material Mined |
142.9 million tonnes |
Strip Ratio |
0.6 : 1 |
Average Plant Throughput (Sulphide + Oxide) |
9.6 Mtpa |
Average Au Sulphide Head Grade |
0.33 g/t |
Average Cu Sulphide Head Grade |
0.21% |
Average Au Oxide Head Grade |
0.45 g/t |
LOM Average Au Sulphide Recovery (combined Flotation & CIL) |
77% |
LOM Average Cu Sulphide Recovery |
87% |
LOM Average Au Oxide Recovery |
81% |
Total Au Ounces Recovered |
766,248 oz. |
Total Cu lbs Recovered |
308.0 Mlbs |
Average Au Production (Years 1-5) |
108,390 oz. |
Average Cu Production (Years 1-5) |
37.3 Mlbs |
LOM Average Au Production |
78,572 oz. |
LOM Average Cu Production |
31.6 Mlbs |
Pre-Production Capital Cost |
$214.2 million |
LOM Sustaining and Closure Capital Cost |
$86.7 million |
LOM Average Cash Cost(1) per Au Ounce (net of by-products) |
$313/oz. |
LOM Average Cash Cost(1) plus Sustaining Cost per Au Ounce (net of by-products) |
$396/oz. |
(1) Cash cost includes all mining, milling & refining, transport, mine-level G&A, and
royalty costs |
Using base case price assumptions of $1,250/oz. gold, $2.50/lb copper and $18.00/oz. silver, Tepal has an estimated $169
million after-tax NPV at a 5% discount rate, an attractive 24% after- tax IRR, and an after-tax payback period of 2.3 years. Base
case LOM revenue split is 54% gold/43% copper/3% silver. The base case economic evaluation used metals prices that are close to
current spot prices and near the median of current medium to long term analyst forecasts. After-tax economics were prepared using
the following assumptions: a 2.5% Net Smelter Return (NSR) royalty, 0.5% Mexican royalty based on precious metals revenue, 7.5%
Mexican royalty based on EBITDA, 12% annual depreciation rate, accumulated tax loss carry forward of US$22.4 million, and a 30%
Mexican income tax rate. The sensitivities of pre-tax and after-tax results to assumed metals prices are as follows:
% Change in Base Case Prices |
-20% |
-10% |
0% |
10% |
20% |
Gold Price (US$/oz) |
$1,000 |
$1,125 |
$1,250 |
$1,375 |
$1,500 |
Copper Price (US$/lb) |
$2.00 |
$2.25 |
$2.50 |
$2.75 |
$3.00 |
Silver Price (US$/oz) |
$14.40 |
$16.20 |
$18.00 |
$19.80 |
$21.60 |
Pre-Tax: |
|
|
|
|
|
NPV5% (US$ millions) |
$31.7 |
$165.6 |
$299.4 |
$433.3 |
$567.2 |
IRR (%) |
10% |
25% |
36% |
46% |
55% |
Payback Period (years) |
3.1 |
2.2 |
1.6 |
1.3 |
1.0 |
After-Tax: |
|
|
|
|
|
NPV5% (US$ millions) |
-$19.3 |
$77.5 |
$169.4 |
$257.2 |
$344.9 |
IRR (%) |
2% |
15% |
24% |
31% |
38% |
Payback Period (years) |
4.5 |
3.0 |
2.3 |
1.9 |
1.6 |
Mineral
Resource
The PEA is based on the current mineral resource estimate for Tepal. The technical report, titled Technical
Report on the Mineral Resources of the Tepal Gold-Copper Project, Michoacán State, Mexico (the "2012 Resource Report"), was
filed on SEDAR on March 29, 2012. Project mineral resources are summarized in the table below:
Total Tepal Project Resource Estimate(1) -
March 2012 |
|
Tonnes |
Au Grade |
Cu Grade |
Ag Grade |
Contained Au |
Contained Cu |
Resource Classification |
|
(g/t) |
(%) |
(g/t) |
(oz) |
(lbs) |
Measured |
34,100,000 |
0.48 |
0.25 |
0.95 |
528,000 |
185,000,000 |
Indicated |
153,700,000 |
0.26 |
0.19 |
1.67 |
1,276,000 |
628,000,000 |
Measured & Indicated |
187,800,000 |
0.3 |
0.2 |
1.54 |
1,804,000 |
813,000,000 |
Inferred |
35,700,000 |
0.16 |
0.15 |
1.68 |
182,000 |
120,000,000 |
|
|
|
|
|
|
|
Oxide and Sulphide Resources(1)- March
2012 |
|
Tonnes |
Au Grade |
Cu Grade |
Ag Grade |
Contained Au |
Contained Cu |
Resource Classification |
|
(g/t) |
(%) |
(g/t) |
(oz) |
(lbs) |
Oxide Measured & Indicated |
21,100,000 |
0.34 |
0.21 |
1.18 |
233,000 |
96,000,000 |
Oxide Inferred |
700,000 |
0.19 |
0.13 |
2.01 |
4,000 |
2,000,000 |
Sulphide Measured & Indicated |
166,700,000 |
0.29 |
0.2 |
1.59 |
1,571,000 |
717,000,000 |
Sulphide Inferred |
35,000,000 |
0.16 |
0.15 |
1.67 |
177,000 |
118,000,000 |
(1) The resource stated in the table conforms to CIM guidelines for reasonable potential
for economic extraction and is not to be confused as reserves. Resource numbers above are rounded to nearest 100,000
tonnes, 1,000 oz Au and 1,000,000 lbs Cu |
Capital Costs
Total pre-production capital cost is estimated at $214 million with the majority of the costs associated with
sulphide and oxide processing plants as well as surface infrastructure. The PEA envisions a two-year construction period. Initial
capital costs will be partially offset by commencing oxide Au/Ag doré production during the second year of construction via a
5,500 tpd oxide processing plant consisting of a ball mill, oxide CIL circuit producing Au/Ag doré and tailings management
facility. Commercial mine production will commence upon commissioning a separate 22,000 tpd sulphide processing plant consisting
of semi-autogenous grinding ("SAG") and ball mills, a flotation circuit producing Cu/Au/Ag concentrate and a sulphide CIL circuit
producing Au/Ag doré, along with tailings management facilities.
Open pit mining and haulage is anticipated to be completed by contract mining companies using their own equipment,
conducted 365 days per year. Electrical power would be supplied by CFE, the federal power authority in Mexico. Pre-production
capital cost includes all costs associated with upgrading an electrical substation located in the community of Tepalcatepec and
adding 20 kilometres of new overhead transmission line from this substation to the Project site. Power line and substation cost
estimates were based on a peak demand load forecast of 28 megawatts and overhead line supplying power at 115kV.
LOM sustaining capital costs are estimated at $87 million with the majority of the costs associated with tailings
and waste rock management and closure costs.
Project capital costs are summarized below:
Capital Costs |
Pre-Production |
Sustaining / Closure |
Total |
|
(US$M) |
(US$M) |
(US$M) |
Mining |
12.4 |
3.0 |
15.4 |
Site Development/Earthworks |
5.5 |
0.0 |
5.5 |
Sulphide Processing Plant |
77.7 |
5.7 |
83.4 |
Oxide Processing Plant |
29.9 |
0.0 |
29.9 |
Tailings & Waste Rock Management |
8.6 |
48.5 |
57.1 |
Surface Infrastructure |
25.2 |
0.0 |
25.2 |
Project Indirects |
10.5 |
0.0 |
10.5 |
EPCM |
15.3 |
0.0 |
15.3 |
Owner Costs |
6.9 |
0.0 |
6.9 |
Closure (Net of Salvage) |
0.0 |
22.9 |
22.9 |
Subtotal Capital Costs |
191.9 |
80.1 |
272.0 |
Contingency 11% |
22.3 |
6.6 |
28.9 |
Total Capital |
214.2 |
86.7 |
300.9 |
Mining
The PEA mine plan would use conventional open pit mining methods with work performed by contract mining companies.
Mineralized material is located in three open pits (North, South and Tizate Pits) and would be mined sequentially, targeting the
highest value material in the initial years of mine life in order to facilitate early capital payback and maximize project
economics. In- pit mineral resources included in the PEA mine plan using 5% mining dilution are as follows:
Mineral Resource (Mine Diluted) Included in PEA Mine
Plan(1)(2) |
|
Tonnes |
Au Grade |
Cu Grade |
Ag Grade |
Contained Au |
Contained Cu |
Resource Classification |
|
(g/t) |
(%) |
(g/t) |
(oz) |
(lbs) |
Measured |
26,800,000 |
0.51 |
0.25 |
0.95 |
438,000 |
150,000,000 |
Indicated |
61,700,000 |
0.28 |
0.20 |
1.58 |
550,000 |
269,000,000 |
Measured & Indicated |
88,500,000 |
0.35 |
0.21 |
1.39 |
988,000 |
419,000,000 |
Inferred |
2,000,000 |
0.19 |
0.18 |
2.73 |
12,000 |
8,000,000 |
(1) The resource stated in the table conforms to CIM guidelines for reasonable potential
for economic extraction and is not to be confused as reserves. Resource numbers above are rounded to nearest 100,000
tonnes, 1,000 oz Au and 1,000,000 lbs Cu |
(2) NSR cut-off for sulphide material is $8.19/tonne milled and for oxide material is
$10.13/tonne milled |
Measured and Indicated resources comprise 98% of the PEA mine plan tonnage, with Inferred resources comprising the remaining
2%.
Processing
The PEA envisions milling of oxide and sulphide material through separate circuits. Oxide material would be milled
at 5,500 tpd through a ball mill and sulphide material would be milled at 22,000 tpd through a separate SAG and ball mill
circuit.
Oxides would be processed through a CIL circuit, producing Au/Ag doré on site that would be shipped for refining.
Oxide Au/Ag doré production is expected to commence during the second year of mine construction in order to offset a portion of
the initial capital cost. Total gold production during the pre-production period would be approximately 21,000 oz.
Sulphides would be processed through a Cu/Au/Ag rougher circuit for copper, gold and silver recovery. The rougher
Cu/Au/Ag concentrate would be reground and processed through a cleaner circuit to produce a copper concentrate with significant
gold credits for shipment to an offshore smelter. Tailings from the Cu/Au/Ag rougher circuit would be sent to a pyrite rougher
circuit to produce a pyrite concentrate. Separate to the Cu/Au/Ag concentrate process, the pyrite concentrate would be combined
with the tailings from the first copper cleaner circuit, with the combined concentrate leached through a CIL circuit to produce
Au/Ag doré on site that would be shipped for refining.
Based on Geologix's previously completed technical work that processed representative material from Tepal's three
pits at G&T Laboratories located in Kamloops, British, the PEA design is expected to produce a concentrate with a copper
grade of 26% and no deleterious elements. The Company believes that the Cu/Au/Ag concentrate will be marketable to smelters.
Operating Costs
Project operating cost estimates are as follows:
Operating Cost |
US$/t |
LOM |
|
processed |
(US$M) |
Mining* |
3.30 |
298.7 |
Processing - Sulphide |
5.49 |
429.7 |
Processing - Oxide |
6.34 |
77.2 |
G&A |
0.75 |
67.4 |
Total OPEX |
9.65 |
873.1 |
*Mining operating cost is $2.16/t mined (excludes waste tonnes not associated with the
1.4Mt of pre-production mining) |
Qualified Persons and 43-101 Disclosure
The technical information contained in this press release is based on information prepared by, or under the
supervision of, Gord Doerksen, P.Eng., VP Engineering for JDS and a Qualified Person for the purpose of National Instrument
43-101, Standards of Disclosure for Mineral Projects of the Canadian Securities Administrators ("NI 43-101").
About Geologix Explorations Inc.
Geologix is a mineral exploration and development company focused on acquiring, exploring, and developing mineral
resource opportunities with the potential to host profitable mining operations. The Company's primary focus is the Tepal
Gold/Copper Project in Michoacán state, Mexico.
This Press Release may contain statements which constitute 'forward-looking' statements, including statements
regarding the plans, intentions, beliefs and current expectations of the Company, its directors, or its officers with respect to
the future business activities and operating performance of the Company. The words "may", "would", "could", "will", "intend",
"plan", "anticipate", "believe", "estimate", "expect" and similar expressions, as they relate to the Company, or its management,
are intended to identify such forward-looking statements. Investors are cautioned that any such forward-looking statements are
not guarantees of future business activities or performance and involve risks and uncertainties, and that the Company's future
business activities may differ materially from those in the forward-looking statements as a result of various factors. Such
risks, uncertainties and factors are described in the periodic filings with the Canadian securities regulatory authorities,
including the Company's Annual Information Form and quarterly and annual Management's Discussion & Analysis, which may be viewed
on SEDAR at www.sedar.com. Should one or more of these risks or
uncertainties materialize, or should assumptions underlying the forward-looking statements prove incorrect, actual results may
vary materially from those described herein as intended, planned, anticipated, believed, estimated or expected. Although the
Company has attempted to identify important risks, uncertainties and factors which could cause actual results to differ
materially, there may be others that cause results not be as anticipated, estimated or intended. The Company does not intend, and
does not assume any obligation, to update these forward- looking statements except as required by applicable Canadian securities
requirements.
Neither the TSX Venture Exchange nor the Investment Industry Regulatory Organization of Canada accepts
responsibility for the adequacy or accuracy of this release.