West African Confirms Sanbrado as +150,000 ounces per Annum Gold Producer by 2019
All amounts stated in US dollars. Base case is stated on a 100% project basis at $1,200/oz
Scarborough , Australia (FSCwire) -
- anbrado open pit feasibility study confirms:
|
|
- Forecast annual production of 150,000 ounces over the first 3 years of project and 93,000 ounces
per annum over the 9 years of current mine life (LOM)
|
|
- 124% increase in Indicated Resources at M1 South, driving new project economics
|
|
- 103% increase in Probable Reserves now 894,000 ounces (16.8Mt at 1.7g/t Au)
|
|
- Two year pay back on $131 million capex (including pre-production mining and contingency)
|
|
- Low All-In Sustaining Costs (AISC) of $708/oz over the first 3 years and $759 over LOM
|
|
- Strong economics - pre-tax NPV5% of $143m, IRR 27% and post-tax NPV5% of $100m, IRR 21%
|
|
- Project fully permitted - mining and environmental permits granted
|
|
- Camp and on-permit water storage construction underway
|
|
- Discussions with project lenders underway – targeting project financing through conventional debt and
equity
|
|
- Ore reserves based on Indicated Resources only, delivered 6 months after M1 maiden resource
|
|
- and less than 12 months after M1 South high-grade discovery
|
- Optimised definitive feasibility study (DFS) underway:
|
|
- Focussing on transition from pit to underground for M1 South
|
|
- Targeting significant boost to project economics by reducing high Y1-2 stripping costs
|
|
- Infill drilling targeting conversion of Inferred Resources within and beneath current ore reserve pit
shells, and extensional drilling at M1 and M5
|
|
- Resource and reserve update M1 and M5
|
|
- Aiming for completion by Q3 2017, fully-funded from existing cash of $17 million
|
Full details, including a Table 1 as required by the JORC Code (2012) for the revised Mineral Resource and
Mineral Reserve estimates, are included in the full report which is available for download from www.westafricanresources.com, www.asx.com.au and www.sedar.com.
Managing Director Richard Hyde commented:
“From high-grade discovery to delivering a robust feasibility study in less than 12 months is an outstanding
achievement, and a credit to our dedicated in-country team and hand-picked independent consultants.
“M1 South is the driving force behind the new project economics and currently represents a high-margin, but
high strip ratio open pit. Consequently, it is likely to be more cost effective to mine M1 South with a smaller
open-pit followed by underground mining. Optimisation work and underground mining studies have commenced and will be
included in an optimised definitive feasibility study by Q3 2017.
“The next steps are straight-forward – we are well-funded to carry out work programs, including completion of an
underground optimisation study, which is likely to drive mining costs significantly lower with further drilling converting
existing Inferred Resources within and beneath reserve pit-shells, and drilling ‘open at depth’ extensions at M1 and M5.
“The open pit feasibility study as it currently stands demonstrates very strong early cashflow, rapid payback of
capital and allows us to advance discussions with project lenders while completing optimisation work, and construction of mine
infrastructure including the camp and early site works.
“We look forward to keeping the market informed with results from our busy 2017 work program.”
Gold developer West African Resources Limited (ASX, TSXV: WAF) is pleased to announce the results of its Open Pit
Feasibility Study, prepared in accordance with the requirements of the 2012 JORC Code and NI 43-101, for the Sanbrado[1] Gold
Project, Burkina Faso. The study envisages an initial 9 year mine life, with strong early cashflow and a rapid payback
of capital.
[1] Formerly known as the Tanlouka Gold Project
Sanbrado Open Pit Feasibility Study – Production and Financial Highlights
|
Base case is stated on a 100% basis and a gold price of $1,200/oz (all amounts in US$)
|
Production Y1-3
|
Average of 150,000oz/yr
|
Production LOM
|
Average of 93,000oz/yr
|
Production Costs1 Y1-3
|
Average Cash Costs of $672/oz (including royalties)
|
Average All-in Sustaining Costs (AISC) of $708/oz
|
Production Costs LOM
|
Average Cash Costs of $717/oz (including royalties)
|
Average All-in Sustaining Costs (AISC) of $759/oz
|
IRR
|
Pre-tax IRR of 27% and 2.1 year payback on initial capital
|
After-tax IRR of 21% and 2.3 year payback on initial capital
|
NPV
|
Pre-tax NPV (5%) of $143M
|
After-tax NPV (5%) of $100M
|
Capex
|
Pre-Production capital of $131 million (including pre-production mining and contingency)
|
Study Mine Life
|
8.75 years
|
Probable Mineral Reserves2,3
|
16.8Mt at 1.7g/t gold containing 894,000 ounces of gold (strip ratio of 5:1)
|
LOM Recoveries
|
90.7% for 810,000 ounces of gold recovered
|
1 Cash costs include all mining and processing costs, site administration, royalties, refining and site
rehabilitation costs. AISC includes Cash costs, sustaining capital, closure costs but excludes head office corporate
costs.
2 Based on Indicated Resources only, in-pit Inferred Resources treated as waste in the study mining
schedule.
3 The average strip ratio of 5.0:1 is inclusive of a strip ratio of 35.6:1 for the M1 South pit.
Competent Persons and Qualified Persons Statement
Information in this announcement that relates to exploration results, exploration targets or mineral resources is
based on, and fairly represents, information and supporting documentation prepared by Mr Brian Wolfe, an independent
consultant specialising in mineral resource estimation, evaluation and exploration. Mr Wolfe is a Member of the
Australian Institute of Geoscientists. Mr Wolfe has sufficient experience which is relevant to the style of
mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent
Person (or “CP”) as defined in the 2012 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources
and Ore Reserves (the JORC Code) and a Qualified Person under Canadian National Instrument 43-101. Mr Wolfe has
reviewed the contents of this news release and consents to the inclusion in this announcement of all technical statements based
on his information in the form and context in which they appear.
Information in this announcement that relates to ore reserves is based on, and fairly represents, information and
supporting documentation prepared by Mr Stuart Cruikshanks, an independent specialist mining consultant.
Mr Cruikshanks is a Fellow of the Australian Institute of Mining and Metallurgy. Mr Cruikshanks has
sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the
activity which he is undertaking to qualify as a Competent Person (or “CP”) as defined in the 2012 Edition of the Australasian
Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (the JORC Code) and a Qualified Person under
Canadian National Instrument 43-101. Mr Cruikshanks has reviewed the contents of this news release and consents to the
inclusion in this announcement of all technical statements based on his information in the form and context in which they
appear.
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the
TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
To view this press release as a PDF file, click onto the following link:
public://news_release_pdf/westafrican02202017.pdf
Source: West African Resources Ltd (TSX Venture:WAF)
To follow West African Resources Ltd on your favorite social media platform or financial websites, please click on the icons
below.
Maximum News Dissemination by FSCwire. http://www.fscwire.com
Copyright © 2017 Filing Services Canada Inc.