Sherritt Announces 2017 Production Results and Guidance for 2018
Sherritt International Corporation (“Sherritt”) (TSX:S):
NOT FOR DISTRIBUTION TO UNITED STATES NEWSWIRE SERVICES OR FOR DISSEMINATION IN THE UNITED STATES
Sherritt International Corporation (“Sherritt”) (TSX:S) today announced its 2017 production results and provided guidance for
expected production, unit costs and capital spending in 2018. All amounts are in US dollars, unless otherwise noted.
Highlights
- Finished nickel and cobalt production at Sherritt’s Moa Joint Venture (JV) was 31,523 tonnes and
3,601 tonnes, respectively, which is within 2017 guidance ranges.
- Nickel production at the Moa JV for 2018 is forecasted at between 31,500 tonnes and 32,500 tonnes on
a 100% basis.
- Cobalt production at the Moa JV for 2018 is forecasted at between 3,500 and 3,800 tonnes on a 100%
basis.
- Net direct cash costs (NDCC) at the Moa JV are forecasted at between $2.50 and $3.00 per pound of
finished nickel reflecting higher anticipated sulphur and energy input costs.
- Gross oil production in Cuba is forecasted at between 4,300 and 4,800 barrels per day in 2018.
- Expected oil production for 2018 reflects a three-year extension of the Puerto Escondido/Yumuri
production sharing contract to 2021, which has received approval from the Executive Committee of the Council of Ministers of the
Republic of Cuba.
- Total capital spending in 2018 is expected to be $94 million, and will include $41 million of capital
spending at the Moa JV and $39 million of spending for Oil and Gas operations. Spending at the Oil and Gas Operations may vary
depending on the rate of collection of overdue receivables.
Summary of 2017 Production Results and 2018 Forecasts
Production volumes 1
|
|
2017
Guidance 2
|
|
2017
Actual
|
|
2018
Guidance
|
Nickel, finished (tonnes, 100% basis) |
|
|
|
|
|
|
Moa Joint Venture |
|
31,500 – 32,500 |
|
31,523 |
|
31,500 – 32,500 |
Ambatovy Joint Venture |
|
36,000 – 39,000 |
|
35,474 |
|
40,000 – 43,000 |
Cobalt, finished (tonnes, 100% basis) |
|
|
|
|
|
|
Moa Joint Venture |
|
3,500 – 3,800 |
|
3,601 |
|
3,500 – 3,800 |
Ambatovy Joint Venture |
|
3,300 – 3,600 |
|
3,053 |
|
3,900 – 4,200 |
Oil – Cuba (gross working-interest, bopd) |
|
13,000 – 14,000 |
|
13,479 |
|
4,300 – 4,800 |
Oil and Gas – All operations (net working-interest, boepd) |
|
7,500 – 8,000 |
|
7,855 |
|
1,900 – 2,100 |
Power (GWh, 33 1/3 % basis) |
|
850 - 900 |
|
848 |
|
750 - 800 |
Nickel and cobalt production at the Moa JV in 2017 was in line with guidance. Ambatovy’s nickel and cobalt production for 2017
were below guidance due to a number of factors, including acid plant equipment failures resulting in reduced acid availability and
reliability issues relating to the pressure acid leach circuit, and other unplanned maintenance activities.
In 2018, nickel and cobalt production at the Moa JV is forecasted at between 31,500 and 32,500 tonnes and 3,500 and 3,800
tonnes, respectively, on a 100% basis. The forecasted totals are consistent with 2017 results, but slightly lower than historical
averages due to a number of factors, including, the impact of heavy rains in Q4 2017 that inhibited mining and is expected to
negatively impact mixed sulphide availability in Q1 2018, and the expected reduced availability of third-party feed due to
increasingly competitive market demand.
Gross oil production in Cuba is forecasted at between 4,300 and 4,800 barrels per day in 2018. The forecast is based on the
renewal of the Puerto Escondido/Yumuri production sharing contract given the approval received from the Executive Committee of the
Council of Ministers of the Republic of Cuba. The production forecast for 2018 also reflects the expiration of the Varadero West
production sharing contract previously disclosed. The oil production forecast does not anticipate any production from Block 10 in
2018 as drilling is yet to be completed.
Nickel and cobalt production at Ambatovy in 2018 is forecasted at between 40,000 tonnes and 43,000 tonnes and 3,900 tonnes and
4,200 tonnes, respectively, on a 100% basis. Forecasted production takes into account the impact that the recent Tropical Cyclone
Ava has had on operations. Production at Ambatovy is currently halted and it is anticipated that, pending completion of repairs and
replacement of certain equipment, production will resume by the end of January. It is also expected that Ambatovy will require a
ramp up period in the first quarter of 2018 before production is stabilized.
The Power Unit is forecasted to produce between 750 and 800 megawatt hours of electricity in 2018. The total is below 2017
production results due to natural oil reservoir declines and the resulting reduction of gas production available for power
generation.
Summary of 2018 Unit Cost Forecasts
Unit Operating Costs |
|
2018
Guidance
|
Metals (NDCC, US$ per pound) |
|
|
Moa Joint Venture |
|
US$2.50 - $3.00 |
Ambatovy Joint Venture
|
|
US$3.00 - $3.50
|
|
|
|
Oil and Gas – Cuba (unit operating costs, C$ per barrel) |
|
C$22.00 - $23.50 |
|
|
|
Power (unit operating costs, C$ per MWh) |
|
C$20.75 - $21.50 |
Net direct cash costs (NDCC) at the Moa JV are forecasted at between $2.50 and $3.00 per pound of finished nickel produced. The
forecast for 2018 is marginally higher than NDCC realized in 2017 due to increased input costs. Net direct cash costs are based on
by-product credits and input commodities that are subject to considerable change given the volatility of cobalt, fertilizers, crude
oil, natural gas and sulphur prices. The NDCC forecast for the Moa JV is also subject to the seasonality of fertilizer sales, which
are typically higher in the second and fourth quarters.
NDCC at the Ambatovy JV are forecasted at between $3.00 and $3.50 per pound of finished nickel produced. The forecast is below
the NDCC realized in 2017 due to expected increased production of nickel and higher byproduct credits offset by higher input
commodity prices, particularly sulphur.
Oil production costs in Cuba are forecasted to be between C$22.00 and C$23.50 per barrel. The forecasted costs are higher than
historical averages due to lower anticipated production in 2018 than in previous years.
Operating costs for Power are forecasted to be between C$20.75 and C$21.50, in line with recent performance.
Summary of 2018 Spending Cost Forecasts
Spending on capital 3
|
|
2018
Guidance
|
Metals |
|
|
Moa Joint Venture (50% basis) and Fort Site (100% basis)
|
|
US$41 (C$52) |
Ambatovy Joint Venture (12% basis)
|
|
US$13 (C$17) |
|
|
|
Oil and Gas – Cuba
|
|
US39 (C$50) |
|
|
|
Power (33 1/3 % basis).
|
|
US$1 (C$1) |
Capital spending at the Moa JV is forecasted at $41 million in 2018, up significantly from 2017. The increase is largely due to
the carry forward of unspent capital on activities and purchase of equipment deferred to 2018. Capital spending in 2018 is also
planned for the replacement of aging trucks and infrastructure, including a fertilizer conveyor and a demineralized water
system.
Capital spending at the Ambatovy JV is forecasted at $13 million. Spending planned for 2018 includes projects to improve
equipment reliability and address corrosion issues as well as for process improvement projects to support the production ramp
up.
Capital spending at the Oil and Gas Unit is forecasted at $39 million. The forecasted spend is primarily for drilling activities
on Block 10 and conducting a seismic program on Block 8A. The timing and amounts of capital spending within the Oil and Gas Unit
will vary depending on the collection of overdue receivables.
About Sherritt
Sherritt is the world leader in the mining and refining of nickel from lateritic ores with projects and operations in Canada, Cuba
and Madagascar. The Corporation is the largest independent energy producer in Cuba, with extensive oil and power operations
across the island. Sherritt licenses its proprietary technologies and provides metallurgical services to mining and refining
operations worldwide. The Corporation’s common shares are listed on the Toronto Stock Exchange under the symbol “S”.
www.sherritt.com
Forward-Looking Statements
This press release contains certain forward-looking statements. Forward-looking statements can generally be identified by the use
of statements that include such words as “believe”, “expect”, “anticipate”, “intend”, “plan”, “forecast”, “likely”, “may”, “will”,
“could”, “should”, “suspect”, “outlook”, “projected”, “continue” or other similar words or phrases. Specifically, forward-looking
statements in this document include, but are not limited to, statements set out in this press release relating to contract
extensions, production results, estimated costs and future capital and funding requirements.
Forward-looking statements are not based on historic facts, but rather on current expectations, assumptions and projections
about future events, including matters relating to the transaction disclosed herein; availability of governmental, regulatory and
third party approvals; and the ability to achieve corporate objectives, goals and plans for 2017. By their nature, forward-looking
statements require the Corporation to make assumptions and are subject to inherent risks and uncertainties. There is significant
risk that predictions, forecasts, conclusions or projections will not prove to be accurate, that those assumptions may not be
correct and that actual results may differ materially from such predictions, forecasts, conclusions or projections.
The Corporation cautions readers of this press release not to place undue reliance on any forward-looking statement as a number
of factors could cause actual future results, conditions, actions or events to differ materially from the targets, expectations,
estimates or intentions expressed in the forward-looking statements. These risks, uncertainties and other factors include, but are
not limited to the risks and uncertainties set out in the Management’s Discussion & Analysis of the Corporation for the period
ending September 30, 2017 and the Corporation’s Annual Information Form dated March 28, 2017, each of which are available on SEDAR
at www.sedar.com. Readers are cautioned that the foregoing list of factors is not exhaustive and should be
considered in conjunction with the risk factors described in this press release and in the Corporation’s other documents filed with
the Canadian securities authorities.
The Corporation may, from time to time, make oral forward-looking statements. The Corporation advises that the above paragraph
and the risk factors described in this press release and in the Corporation’s other documents filed with the Canadian securities
authorities should be read for a description of certain factors that could cause the actual results of the Corporation to differ
materially from those in the oral forward-looking statements. The forward-looking information and statements contained in this
press release are made as of the date hereof and the Corporation undertakes no obligation to update publicly or revise any oral or
written forward-looking information or statements, whether as a result of new information, future events or otherwise, except as
required by applicable securities laws. The forward-looking information and statements contained herein are expressly qualified in
their entirety by this cautionary statement.
1 Nickel and cobalt production are presented on a 100% basis. Sherritt’s share varies by business unit, with the Moa JV
being a 50% joint venture, Ambatovy a 12% investment in an associate, and Power a 331/3% interest.
2 All 2017 guidance figures are as of Q3 2017 as reported on October 24, 2017.
3 Capital spend is based on Sherritt’s ownership interests in the Moa Joint Venture (50%); Fort Site (100%), Ambatovy (12%),
Power (331/3%).
Sherritt International Corporation
Joe Racanelli, 416-935-2451
Director of Investor Relations
Toll-Free: 1-800-704-6698
investor@sherritt.com
View source version on businesswire.com: http://www.businesswire.com/news/home/20180112005290/en/