VANCOUVER, Nov. 8, 2018 /CNW/ - Lundin Gold Inc.
("Lundin Gold" or the "Company") (TSX: LUG, Nasdaq Stockholm: LUG) is pleased to announce its results for the three and nine
months ended September 30, 2018. All amounts are in U.S. dollars unless otherwise
indicated.
Please view PDF version of News
Release.
"With overall construction just over a third complete and a significant portion of the Project's capital committed, Fruta del
Norte remains on track for first gold expected around this time next year. This makes us one of the largest and
highest-grade gold projects coming online in the near term," said Ron Hochstein, Lundin Gold's President and CEO. "Underground mine development is progressing on schedule and based on
planned rates, we anticipate reaching the orebody in the first quarter of 2019."
Highlights
Fruta del Norte Gold Project ("Fruta del Norte" or the "Project")
- Overall engineering was 63% complete and construction 34% complete.
- Cumulative advance in the Kuri and K'isa declines was 3.3 kilometres ("km").
- Process plant excavation is done, and concrete is 40% complete.
- Grinding building steel erection is underway.
- North Access Road was substantially complete and being used by commercial vehicles.
- Powerline construction is ongoing on three separate work fronts.
- Updated mine plan and re-estimate of the Project's capital cost and operating cost were completed. It resulted in
increases in the Project's NPV 5% ($786 million from $717 million)
and IRR (17.5% from 16.3%). The new capital cost estimate increased only marginally by $8.0
million to $692 million. At the same time, the estimated all-in sustaining cost
dropped to $583 per ounce of gold from $609 per ounce of gold.
Exploration
- Mapping, geochemical sampling and permitting required for future drilling continues on a number of epithermal gold-silver
targets in the central and southern Suarez Basin, and the Gata Salvaje target area to the west of the Basin.
Fruta del Norte Gold Project
Mine Development
As at September 30, a total of 3.3 km of underground mine development had been achieved, with
1,565 metres ("m") and 1,760 m in the Kuri and K'isa declines, respectively. Daily advance
rates continued to be above target throughout the quarter with an average advance rate of 6.2 m per
day in Kuri and 7.0 m per day in K'isa in September, versus a target of 4.0
m per day and 3.8 m per day, respectively. The increase in advance rates are the
result of better than anticipated ground conditions, less water than expected and higher contractor productivities.
Process Plant Construction
Process plant foundations are well advanced and steel erection has started on the grinding building. Fabrication of
process plant equipment is on track and the flotation cells, mills, CIL tanks and thickeners are expected to arrive on site by
the end of this year.
Major Site Earthworks
The North Access Road was substantially complete and is being used by commercial vehicles. The tailings storage facility
dam and basin clearing has started, while the temporary construction coffer dams are finished. Work also began on the east
diversion ditch. Polishing pond earthworks are almost done, and liner installation is underway.
Paste plant access road and site preparation has begun and the fresh air raise access road was completed.
Other
The Company received the Mountain Pass Quarry Environmental License and is in the final stages of negotiating rights to
develop the quarry with local government. Construction of the powerline started on three fronts in September.
Financial Results
|
|
|
(in thousands, except per share amounts)
|
Three months ended
September 30,
|
Nine months ended
September 30,
|
|
|
2018
|
|
2017
|
|
2018
|
|
2017
|
|
|
|
|
|
|
|
|
|
Results of Operations:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Net income (loss) for the period
|
$
|
7,270
|
$
|
(16,032)
|
$
|
1,423
|
$
|
(21,634)
|
|
|
|
|
|
|
|
|
|
Income (loss) per share
|
|
|
|
|
|
|
|
|
Basic
|
|
0.03
|
|
(0.13)
|
|
0.01
|
|
(0.18)
|
Diluted
|
|
0.03
|
|
(0.13)
|
|
0.01
|
|
(0.18)
|
|
|
|
|
|
|
|
|
|
|
|
|
(in thousands)
|
|
As at
September
30 2018
|
|
As at
December
31, 2017
|
Financial Position:
|
|
|
|
|
Cash
|
|
291,599
|
|
35,018
|
Working capital
|
|
290,398
|
|
26,794
|
Property, plant and equipment
|
|
368,829
|
|
142,598
|
Mineral properties
|
|
256,769
|
|
246,387
|
Total assets
|
|
1,007,287
|
|
481,729
|
Long-term debt
|
|
351,591
|
|
217,940
|
|
|
|
|
|
|
|
|
|
|
The Company's net income in the third quarter of 2018 is due to the revaluation of the Company's long-term debt, as more fully
explained below, and was offset by a foreign exchange loss from its substantial holdings of U.S. dollar cash at its Canadian
entities during the quarter compared to a foreign exchange loss of only $0.8 million in the third
quarter of 2017.
The Company generated net income of $1.4 million in the nine months ended September 30, 2018 compared to a loss of $21.6 million in the same period of
2017. This is mainly due to the revaluation of the Company's long-term debt and recognition of a substantial foreign
exchange gain. Partially offsetting these gains were higher salaries and benefits during the nine months ended September 30, 2018 compared to the same period in 2017 due to the performance incentive plan payment to the
Company's employees.
Derivative gains or losses
During the third quarter of 2018, the Company recorded a derivative gain from the fair value revaluation of its long-term debt
of $17.9 million compared to a derivative loss of $8.3 million
recognized in the third quarter of 2017. For the nine months ended September 30, 2018, the
Company has recorded a derivative gain of $12.8 million compared to a derivative loss of
$3.9 million in the same period in 2017.
Liquidity and Capital Resources
As at September 30, 2018, the Company had cash of $291.6 million
and a working capital of $290.4 million compared to cash of $35.0
million and a working capital balance of $26.8 million at December
31, 2017. The change in cash was primarily due to net proceeds from the private placement in March 2018 of $396.5 million and the final drawdown of $110 million under the gold prepay and stream credit facilities. This is offset by costs incurred for the
development of the Fruta del Norte Project of $193.3 million, general and administration costs of
$14.3 million and exploration expenditures of $5.0 million.
Outlook
The Company is focused on advancing the Project on schedule through to first gold production in the fourth quarter of
2019. The following activities are planned over the next twelve months:
- Completing detailed engineering.
- Completing process plant construction and starting commissioning.
- Starting mine operations and mining ore to stockpiles.
- Advancing underground declines across the ore body to the bottom of the fresh air raise.
- Completing construction of the site infrastructure buildings such as the laboratory, reagent storage, mine dry and
administration.
- Completing the construction of the power transmission line and connecting to the national grid at the Bomboiza
substation.
- Signing the Mountain Pass Quarry exploitation agreement and developing the quarry.
- Completing construction of the tailing storage facility.
- Completing the design and supply of the paste plant and commencing construction.
- Obtaining permits and starting construction of the Zamora River bridge in El Pindal.
The Company has substantially agreed to the terms of a cost overrun facility (the "COF") with a provider. Completion of
the COF is a condition precedent to the initial draw down of the senior debt facility, expected to occur in the first quarter of
2019, and is now subject to acceptance by the Company's lenders and final documentation.
Exploration continues to focus on developing drilling targets through mapping and geochemical sampling at the Suarez Basin and
Gata Salvaje targets. Drill permitting continues for a number of epithermal gold-silver target areas around the Suarez Basin.
Qualified Person
The technical information relating to the Fruta del Norte Project contained in this press release has been reviewed and
approved by Ron Hochstein P. Eng, Lundin Gold's President and CEO who is a Qualified Person under NI 43-101. The
disclosure of exploration information contained in this press release was prepared by Stephen Leary, MAusIMM CP(Geo), a
consultant to the Company, who is a Qualified Person in accordance with the requirements of NI 43-101.
Additional Information
The Company's consolidated financial statements for the three and nine months ended September 30, 2018 and related
management's discussion and analysis are available on the Company's website at www.lundingold.com or under its profile on SEDAR at www.sedar.com.
The information in this release is subject to the disclosure requirements of Lundin Gold under
the EU Market Abuse Regulation. This information was submitted for publication November 8, 2018 at
3:00 p.m. PT through the contact persons set out below.
About Lundin Gold
Lundin Gold, headquartered in Vancouver, Canada, is
developing its wholly-owned Fruta del Norte gold project in southeast Ecuador. Fruta del Norte is one of the world's
largest, highest-grade gold projects currently under construction. The Company's board and management team have extensive
expertise in mine construction and operations, and are dedicated to advancing this project through to first gold production in
the fourth quarter of next year.
The Company operates with transparency and in accordance with international best practices. Lundin Gold is committed
to delivering value to its shareholders, while simultaneously providing economic and social benefits to impacted communities,
fostering a healthy and safe workplace and minimizing the environmental impact. The Company believes that the value created
through the development of Fruta del Norte will benefit its shareholders, the Government and the people of Ecuador.
Follow Lundin Gold on
Twitter
Caution Regarding Forward-Looking Information and Statements
Certain of the information and statements in this press release are considered "forward-looking information" or
"forward-looking statements" as those terms are defined under Canadian securities laws (collectively referred to as
"forward-looking statements"). Any statements that express or involve discussions with respect to predictions,
expectations, beliefs, plans, projections, objectives, assumptions or future events or performance (often, but not always,
identified by words or phrases such as "believes", "anticipates", "expects", "is expected", "scheduled", "estimates", "pending",
"intends", "plans", "forecasts", "targets", or "hopes", or variations of such words and phrases or statements that certain
actions, events or results "may", "could", "would", "will", "should" "might", "will be taken", or "occur" and similar
expressions) are not statements of historical fact and may be forward-looking statements.
By their nature, forward-looking statements and information involve assumptions, inherent risks and uncertainties, many of
which are difficult to predict, and are usually beyond the control of management, that could cause actual results to be
materially different from those expressed by these forward-looking statements and information. Lundin
Gold believes that the expectations reflected in this forward-looking information are reasonable, but no assurance can be
given that these expectations will prove to be correct. Forward-looking information should not be unduly relied upon.
This information speaks only as of the date of this press release, and the Company will not necessarily update this information,
unless required to do so by securities laws.
This press release contains forward-looking information in a number of places, such as in statements pertaining to: the
anticipated timing of production and the progress of the development, construction and operation of the Project, improvements to
site logistics and completion of site and powerline infrastructure and the acquisition of land and surface rights, the success of
the Company's exploration plans and activities, exploration and development expenditures and reclamation costs, timing and
success of permitting and regulatory approvals, project financing and future sources of liquidity, capital expenditures and
requirements, future tax payments and rates, cash flows and their uses.
Lundin Gold's actual results could differ materially from those anticipated. Management
has identified the following risk factors which could have a material impact on the Company or the trading price of its shares:
the ability to arrange financing and the risk to shareholders of dilution from future equity financings; the ability to maintain
its obligations under the gold prepay and stream credit facilities, the senior debt facility and other debt; risks related to
carrying on business in Ecuador; volatility in the price of gold; the timely receipt of
regulatory approvals, permits and licenses; risks associated with the performance of the Company's contractors; risks inherent in
the development of an underground mine; deficient or vulnerable title to mining concessions and surface rights; shortages of
critical resources, labour and key executive personnel, such as input commodities, equipment and skilled labour, and the
dependence on key personnel; risks associated with the Company's community relationships; unreliable infrastructure; volatility
in the market price of the Company's shares; the potential influence of the Company's largest shareholders; uncertainty
with the tax regime in Ecuador; measures required to protect endangered species; the cost of
compliance or failure to comply with applicable laws; exploration and development risks; the accuracy of the Mineral Reserve and
Resource estimates for the Fruta del Norte Project; the Company's reliance on one project; risks related to artisanal and illegal
mining; uncertainty as to reclamation and decommissioning; risks associated with the Company's information systems;
competition in the mining industry; the ability to obtain adequate insurance; risks of bribery or corruption; the potential for
litigation; and limits of disclosure and internal controls.
There can be no assurance that such statements will prove to be accurate, as Lundin Gold's
actual results and future events could differ materially from those anticipated in this forward-looking information as a result
of the factors discussed in the "Risk Factors" section in Lundin Gold's Annual Information Form
dated March 20, 2018, which is available under the Company's profile at www.sedar.com.
Figure 1. Fruta del Norte
project site September 2018 (Full Resolution)
Figure 2. North Access Road was substantially complete and being used by commercial vehicles (Full Resolution)
Figure 3. Process plant
grinding building steel is progressing (Full Resolution)
Figure 4. New permanent
maintenance shop will have six bays (Full Resolution)
Figure 5. Powerline
construction is ongoing on three fronts (Full Resolution)
SOURCE Lundin Gold Inc.
View original content to download multimedia: http://www.newswire.ca/en/releases/archive/November2018/08/c1059.html