Join today and have your say! It’s FREE!

Become a member today, It's free!

We will not release or resell your information to third parties without your permission.
Please Try Again
{{ error }}
By providing my email, I consent to receiving investment related electronic messages from Stockhouse.

or

Sign In

Please Try Again
{{ error }}
Password Hint : {{passwordHint}}
Forgot Password?

or

Please Try Again {{ error }}

Send my password

SUCCESS
An email was sent with password retrieval instructions. Please go to the link in the email message to retrieve your password.

Become a member today, It's free!

We will not release or resell your information to third parties without your permission.

December 2018 Quarterly Report

WFRSF

SUBIACO, WA / ACCESSWIRE / January 22, 2019 / Gold developer West African Resources Limited (ASX, TSXV: WAF) is pleased to report progress on its Sanbrado Gold Project ("Sanbrado"), Burkina Faso, for the quarter ending 31 December 2018.

Highlights

Project Development Summary

  • Underground mining contract awarded to Byrnecut
  • Mill package awarded to Outotec, order placed for 4MW SAG and ball mills
  • EPCM contract for Sanbrado awarded to Lycopodium
  • Earthworks, camp and box cut for underground access commenced by WAF construction team
  • Further Key hires completed for construction, operations and security teams

M1 South Diamond Drilling

  • 1km diamond hole intercepted extensive visible gold returning 25m at 15.03 g/t Au
  • Intercept located 220m vertical beneath existing Probable Ore Reserves, confirms potential to extend M1 South underground mine life past 4.5 years
  • Parallel high-grade zone at M1 South intercepted 300m below surface, 180m east of main zone 2m at 138.4 g/t Au and 5.5m at 15.5 g/t Au
  • Infill drilling returns 21.5m at 15.3 g/t and 14.5m at 19.9 g/t Au

Corporate Summary

  • West African fully funded through to gold production in 2020 at Sanbrado
  • US$200 million finance facility secured with Taurus Funds Management Pty Ltd
  • Fully underwritten institutional Share Placement completed raising A$43.2 million
  • Share Purchase Plan offer for up to A$5 million enabling retail shareholders to participate in Sanbrado project funding closes January 25, 2019
  • Updated security protocols and procedures for staff and contractors in Burkina Faso

December 2018 Quarter Summary

  • 5,656m drilled
  • A$7.8m exploration and mine development expenditure
  • A$4.2m administration costs (including costs associated with project finance raising - debt and equity)
  • A$66.4m cash at bank at 31 December 2018

March 2019 Quarter Plans

  • Completion of feasibility study optimisation and update
  • Exploration drilling near surface targets in trucking distance to Sanbrado
  • Award of open pit mining contract
  • Completion of stage 1 camp (120 rooms), admin building, clinic and temporary power station
  • Major mechanical and electrical equipment procurement
  • Structural steel and platework fabrication commencement

Click here to view the full quarterly report

SOURCE: West African Resources Limited

Tags:


Get the latest news and updates from Stockhouse on social media

Follow STOCKHOUSE Today