adjusting for outage
Thanks for that dispatch website. Very helpful.
Adjusting (roughly) for long Jan outage, but not the other two short outages, very roughly, for first 882 hours, would get average pool price of: $106 per MWhr, and avg production of 236 MW.
The heat rate would also likely not be as good at the 8.1 from their presentation.
So this would give an estimate somewhere of earnings before finance and tax some amount lower than about C$ 10 MM for the first 882 hours. Still good.