Post by
illusion81 on May 28, 2023 10:02pm
Working back from September's "conservative" timeline
Next week we enter June, which leaves 3 months before we hit CRE''s own proclaimed conservative timeline. I believe there are a number of posters on this board that are either involved in some way in the business of mining or are at least pretty well versed in it from other investments and research. With this being the case, I wanted to put out the question to this group around when would be the absolute latest that CRE would need to be financed to keep their current timeline in tact? If they want to be stripping trees in September, then I think it's only logical that they have to have purchased machines and have secured a labour force to this work. What else is needed? A make shift camp of sorts for the workers? How late can they wait to secure all this? I don't believe there was any mention from management to get this work started prior to securing a partner and financing. So if this is true and if it takes "x" weeks/months on average to get the right man power and machinery on the ground to get the work started, then by knowing "x" we should be able to determine what is the latest date by which they need to have the partner and financing in place. Any educated guesses for what "x" is equal to are welcome.
Comment by
illusion81 on May 29, 2023 8:45am
Appreciate the insight, Tinker. If it's at least a month that they would need then end of July to complete the financing should be the latest. That's also considering if they don't want to use the $ that's already in the bank to get things going on the job site.
Comment by
tinker901 on May 29, 2023 9:36am
I spoke to M. Laperriere las week and September is still on.
Comment by
Wheeler on May 29, 2023 10:18am
Has anyone asked management what they mean by conservative ? Were all their previous timelines not conservative? I'm a little confused by this.