RE:Canada Green house status
RE:Canada Green house statusHi Futureboss, As of May 2018, they have completed 150,000 sq ft of erected shell with 70% of the floors poured. The remaining 67,000 sq ft including flowering rooms, packaging, oil extraction and laboratory area is expected to be completed by Q4 (MD&A). Currently the license for the Canadian facility is 6,250KG, automation machines should be installed in the coming months and adding new rooms progressively when completed. We are getting there, just taking some time to complete. Hope this helps.
futureboss wrote: Hi new to the board...could someone tell me the the status of the Canadian build out ? I cant seem to find confirmed sq feet currently? Thxs