Join today and have your say! It’s FREE!

Become a member today, It's free!

We will not release or resell your information to third parties without your permission.
Please Try Again
{{ error }}
By providing my email, I consent to receiving investment related electronic messages from Stockhouse.

or

Sign In

Please Try Again
{{ error }}
Password Hint : {{passwordHint}}
Forgot Password?

or

Please Try Again {{ error }}

Send my password

SUCCESS
An email was sent with password retrieval instructions. Please go to the link in the email message to retrieve your password.

Become a member today, It's free!

We will not release or resell your information to third parties without your permission.

Nevada Copper Achieves Major Milestone

T.NCU

VANCOUVER, BRITISH COLUMBIA--(Marketwired - Feb. 26, 2015) - Nevada Copper Corp. (TSX:NCU) ("Nevada Copper" or the "Company") is pleased to announce that it achieved a major milestone at its Pumpkin Hollow project by way of reaching the 1,900 foot main haulage level at its 24-foot diameter concrete-lined production sized shaft.

A concrete-lined production shaft to the level of the main workings further de-risks the Pumpkin Hollow project and was defined as project milestone in early 2011. During 2012, after the official ground breaking in February, shaft related construction activities included: shaft foundation ("sub-collar"); "pre-sink" to 99 feet; installation of a production-sized hoist and control room; erection of a permanent head-frame; plus related surface facilities. Early in 2012, management made a decision to forego a temporary sinking hoist arrangement and take the additional time to purchase and construct a production-sized hoist, hoist control room and erect a permanent head-frame. This decision is expected to accelerate future project construction activities.

In May 2013 with all facilities in place and operational with the "pre-sink" completed, shaft sinking resumed below 99 feet. During progress of the shaft towards the 1,900 foot main haulage level, an effective dewatering program was implemented. This consisted of drilling two fully commissioned dewatering wells (1,500 and 2,070 feet deep), with water disposal by way of eight permitted rapid infiltration basins, and summer agriculture irrigation.

While the 1,900 foot level milestone was delayed from our initial estimate, it was delivered within an acceptable timeframe considering the Company's decision to purchase a production-sized hoist and erect a permanent head frame.

Nevada Copper will now move forward with approximately 700 feet of lateral development on the 1,900 foot main haulage level and construction of drill stations for purposes of locating and expanding high grade ore to enhance an already high grade profile. The lateral development will also establish key work areas underground for future development, and provide for future access to the East ore zones. Drilling was suspended on the underground deposits in 2011 in view of the then-outlined proven and probable mineable reserves with a view of resuming drilling upon accessing the main haulage level. The current underground drilling program is expected to commence in April and will consist of 26,000 feet (7,900 meters) of drilling.

The shaft is currently within the host skarn related rocks where little or no water is reporting to the bench. Good ground conditions are expected for the lateral development work. As lateral development and drilling continues on the 1,900 level, the shaft will be deepened first to 2,050 and then to its final depth of 2,150 feet. At the 2,050 level, lateral development around the shaft will provide for a station and development to the west and north in Q3-2015. In addition, a temporary sump will be cut out at the level (which will be used for temporary storage, equipment safety bay, and eventually become the bottom of a waste pass). The lateral development work is the minimum necessary in order to continue sinking the remainder of the shaft, while still allowing for equipment delivery to the 2,050 level for future mine development.

About Nevada Copper

The Company's advanced stage Pumpkin Hollow project in Nevada consists of a fully permitted, 6,500 tons/day underground copper mine development, with the main shaft in construction, and a nearby 70,000 tons/day open pit copper project with permits expected in Q2-2015. Projected average copper production for the first five years is 75 million lbs./year from the Stage 1 underground mine, and 220 million lbs./year from the Stage 2 open pit mine. The project is located near Yerington, Nevada, close to road, rail, and power infrastructure, and with all future water supply requirements met.

For further information please visit the Nevada Copper corporate website (www.nevadacopper.com) and visit our Pumpkin Hollow virtual tour.

Qualified Persons

The technical information in this release has been reviewed and approved by Gregory French, P.G., Vice-President, Exploration & Project Development, Timothy D. Arnold, P.E., Vice President Operations, and Robert McKnight, P. Eng., Executive Vice-President and CFO of Nevada Copper, all of whom are Non-independent Qualified Persons within the meaning of NI 43-101.

NEVADA COPPER CORP.

Giulio T. Bonifacio, President & CEO

We seek safe harbour.

Nevada Copper Corp.
Eugene Toffolo
VP, Investor Relations & Communications
604-683-8266 or Toll free: 1-877-648-8266
etoffolo@nevadacopper.com

Nevada Copper Corp.
Robert McKnight, P.Eng., MBA
Executive Vice President & CFO
604-683-1309
bmcknight@nevadacopper.com